Fifteen Metropolitan, Municipal and District Assemblies in the Northern Region have been captured in the 2018 Auditor-General’s report for misapplication and diversion of monies amounting to ¢483,690.68.
A total of ¢47,056,420.30 was allocated to the 28 district assemblies in the Northern region for the year 2018 out of which ¢10,376,711.28 was deducted at source for service providers the assemblies owe, leaving a net of cash transfer of ¢36,679,70.02.
The affected assemblies have been directed to refund the amount.
Two assemblies, North Gonja and Sawla-Tuna-Kalba are to refund ¢240,708.00 as impress to nine officers for various activities which were not retired as at the end of 2018.
The Tatale-Sanguli Assembly misapplied GH₵17,809.41 of the Persons with Disabilities (PWDs) fund on re-current expenditure which is was not related to the PWDs. The AG has recommended the money be paid back to the PWDs accounts.
The report faulted East Gonja Municipal Assembly for failing to recover debts owed the Planting for Food and Jobs Programme after harvest amounting to ¢294,275.00.
The Auditor-General recommended that Zoomlion refunds ¢4,748, 550.000 to ten assemblies for its fumigation exercise.
The Northern Regional Auditor, C. K Normanyo explained that they were asked to refund because officers mandated to certify the fumigation exercise carried out, failed to respond to the audit observation.
The Savelugu Municipal, Mamprugu Mogduri and North Gonja assemblies are to refund ¢64,849.71 as unpresented payment vouchers unaccounted for, due to poor record-keeping and supervision by the finance officers.
The Auditor-General asked the Tamale Metropolitan Assembly to refund ¢917,756.26 Ghana cedis misapplied under the Ghana Urban Management Pilot Project (GUMPP). The Auditor-General in its 2018 report, found TMA to have misapplied the funds contrary to section 361 of the operational manual.
Cost overrun due to delays and abandoned projects in eight districts resulted in ¢1.859.800.66. The Auditor-General recommended that 22 projects in these districts be completed before new ones are awarded.
The districts are Sagnarigu Municipality, Nanumba North, Mion, Bole, Tamale Metropolitan, Gushiegu, Sawla-Tuna-Kalba and Kpandai.
The Auditor-General also recommended that ¢23,378 be paid to three contractors without work done in the Sagnarigu, West Gonja and Bole assemblies be refunded to the assemblies.
Latest Stories
-
Version of AI tool ‘too powerful for public’ released to public
23 minutes -
World’s largest chipmaker does not rule out price rises as costs increase
33 minutes -
Ghana at the 2026 FIFA World Cup: Predictions and Realistic Chances
1 hour -
Video: Black Stars players jam to Black Sherif’s ‘Top of the Morning’ banger
2 hours -
GIISDEC to launch data centre to boost transparency and traceability
2 hours -
Ghana pushes private sector-led investment drive in West Africa’s gas sector
2 hours -
Energy Commission launches renewable energy champions challenge
2 hours -
Air Canada pilot accused of flying for 17 years without correct licence
3 hours -
ICC suspends top prosecutor after investigating misconduct allegations
3 hours -
Does referee case show FIFA has lost control of its own World Cup?
3 hours -
Williams rolls back the years on return at Queen’s
3 hours -
UK: Driving test booking rules tightened after thousands of no shows
3 hours -
Real Madrid’s £130m Alvarez bid rejected
3 hours -
[Video] ‘Occupational hazard’ – Mahama’s comment after South African flight interrupted his speech at Accra Int’l airport
4 hours -
Gov’t allocating World Cup slots to NDC MPs, party supporters – Habib Iddrisu
4 hours