The Performance Audit Report on Capital Projects funded through District Development Facilities in 30 Districts Assemblies compiled by the Auditor-General has uncovered cases of payment for no work done.
Findings of the Audit Report on payment and work done showed that monies were disbursed for non-executed works resulting in overpayments.
“For example, the pavement for work at the taxi station of Ho barracks was paid in full when only 50 per cent of the work was done.
In some instances, items that were specified for installation were omitted yet payments were made like the U drain around the Bibiani District Police Headquarters, which was not done yet paid in full,” it noted.
The report said in Prestea Huni Valley, the specified depth of the borehole at Gordon Community was 35 to 45 metres for a Mechanised pump however investigations revealed that the depth was not up to that.
“Upon completion of the drilling, an AFRIDEV hand pump recommended for a depth of 16.6 to 30 metres was installed and therefore was not deep enough to pump out water from below 35meter when it was completed and handed over,” it said.
The report said the contractor was paid in full for a mechanised borehole when he provided a manual hand pump borehole and the community had no water.
“We observed that Assemblies make payment for no work done due to insufficient due diligence and familiarisation. In the individual reports, we have recommend for disallowance and Surcharge of the individuals concerned,” it stressed.
The report stated that the occurrences were due to a combination of lack of due diligence on the part of the District Management Team, District Works Engineer (DMEs) and familiarization between DWEs and Contractors.
It said, “Contractors and works engineers get to familiarize with each other to the extent that a suggestion by a contractor for DWE to increase the work done beyond the actual work to cater for delayed payments are accepted and paid for.”
The report said payment for work done except for mobilization was based on measured work at the time of preparing Interim Payment Certificate (IPC).
It noted that the DWEs, upon request by contractors measure the amount of work done, cost it, and prepare certificates to cover the amount.
Per the rule, it said the DMT validates the work against the IPC quantities before approval was given for payment.
Latest Stories
-
Prof. Gyampo dismisses NPP’s ‘Democracy Under Attack’ protest as face-saving tactic
11 minutes -
Kadjebi-Asato SHS seals 2026 NSMQ nationals place after commanding regional display
13 minutes -
NSMQ 2026: Nkonya SHS clinches first Oti Region ticket after low-scoring qualifier
17 minutes -
MF report reveals $1.7 billion BoG gold purchase losses – 8 times higher than the previously reported $214 million
18 minutes -
Amnesty International Ghana urges Parliament to fast-track Anti-Witchcraft Accusation Bill
21 minutes -
Businesses urged to treat AI as a strategic capability, not just a cost-cutting tool
35 minutes -
Lawyers for Sammy Gyamfi deny claims linking him to alleged GH¢200m GoldBod scandal
36 minutes -
NPP rejects Supreme Court’s delegate system ruling, warns of cost implications
43 minutes -
African labour leaders demand worker-centred energy transition ahead of COP31
45 minutes -
Investors’ confidence in Ghana’s recovery is encouraging – Ato Forson
46 minutes -
PNP joins NPP’s ‘Save the Judiciary’ demonstration, cites concerns over selective justice
48 minutes -
Bribery laws should be enforced instead of scrapping delegate system – Evans Nimako
48 minutes -
Supreme Court ruling on delegate system will impose huge financial burden on political parties – Evans Nimako
48 minutes -
Sammy Gyamfi threatens legal action over claims linking him to GH¢200m GoldBod allegation
50 minutes -
Orchestrating national wealth: The urgent case for operationalising a Ghana Minerals & Commodities Exchange Authority
58 minutes