The 2024 Auditor-General’s report on the public accounts of Ghana has uncovered significant lapses in contract management across public institutions, with irregularities amounting to a staggering GH¢871,818,832. The losses stem largely from public boards, corporations, and statutory institutions failing to enforce key contract provisions and honour overdue obligations.
Predominant among the irregularities is the non-payment of interim payment certificates (IPCs) issued to contractors, which alone triggered GH¢615.9 million in outstanding interest liabilities. The report flags this as a recurring issue, pointing to weak oversight and delayed payments as the root causes.
“These were mainly related to the non-payment of overdue payables and failure to ensure that provisions in contracts are enforced,” the report stated.
The Auditor-General is calling on management of public boards, corporations, and other statutory institutions that were affected to strengthen internal controls and enforce contract clauses. This, the report stresses, is crucial in safeguarding public funds and restoring discipline in public procurement and contract execution.
“We therefore urged Managements to strengthen controls over contracts and ensure that clauses in contracts are enforced to the letter to safeguard the rights of Public Boards, Corporations, and other Statutory Institutions,” the report urged.
The sharp increase
The 2024 figure is by far the highest in the past six years, underlining how contract mismanagement has ballooned in recent times. A look at the historical data shows that while past irregularities ranged between GH¢4 million and GH¢280 million, 2024's GH¢871.8 million represents a sharp escalation.

The trend points to a growing gap in contract administration discipline, especially when interim contractor payments are delayed or left unsettled.
The report’s findings reinforce growing concerns about inefficiencies in the country’s public financial management systems and the fiscal risks they pose, particularly at a time when the country is under an IMF-backed economic programme that demands stricter controls on spending and improved accountability across government institutions.
Latest Stories
-
AAC secures 750 acres of irrigated land to drive commercial vegetable production under MoFA partnership
3 minutes -
Washington wildfire arson suspect twice linked to other blazes, authorities say
6 minutes -
EU hands over two patrol boats to Ghana Navy to boost maritime security
6 minutes -
Fibi Hammond releases new gospel single ‘You Never Fail’
8 minutes -
Muslim and Christian leaders unite against rising student indiscipline in schools
10 minutes -
GSA: New vehicle rules are not a ban on used cars
11 minutes -
Australian teen who killed UK woman has reduced sentence overturned
19 minutes -
Pakistan restricts international media reporting
19 minutes -
Africa spends over US$14bn annually on imported medicines; Ghana must boost local production – Health Minister
28 minutes -
NSMQ 2026: Nifa SHS ends Okuapemman’s four-year run at national championship
28 minutes -
Three confirmed dead in Aboso explosion as police probe suspected illegal storage of explosives
30 minutes -
IMF backs slower fiscal tightening for Ghana from 2027 to allow more development spending
33 minutes -
Michigan Democrats locked in tight battle to earn Senate nomination in crucial seat
33 minutes -
Old Tafo Assembly to intensify sanitation law enforcement as clean-up campaign gathers pace
37 minutes -
New SHS Selection Guidelines: 620,000 students complete School choices as process ends Friday
38 minutes