All sections of the Achimota-Ofankor Road will be completed and opened to traffic in May this year.
The opening of the 5.7-kilometre, three-lane dual carriageway with three interchanges and service roads is expected to enhance driving on the corridor and significantly reduce the ‘go-slow’ that keeps motorists in traffic for hours.
The Resident Engineer on the project, Mr Shelter Yao Lotsu, said 91.6 per cent of the major works had been completed, adding that “all sections of the road will be opened, the main carriageway, as well as the service roads”.
He, however, stated that the contractor, Messrs China Railway Wuju (Group) Corporation, had requested for a four-month extension to enable it to complete a storm drain and a footbridge at the Taifa Junction.
Mr Lotsu said that had become necessary following a difficulty the contractor encountered with the foundation works of the footbridge.
“The foundation of that footbridge has consequently been redesigned and is currently under construction,” he stated.
The storm drain was to help reduce the perennial flooding at Taifa and its environs, he said, adding that work on both the footbridge and the storm drain would be completed in September this year.
Work on the Achimota-Ofankor Road project started on November 15, 2006 and was originally scheduled for completion by November 15, 2009.
Due to some variations to the project, the completion date was revised, first to May 15, 2011 and finally to May 15, 2012.
The project forms part of the southern part of the urban section of the dualisation of the Accra-Kumasi Road, also referred to as N6.
It starts from the Neoplan Junction in the south and ends at the Ofankor Barrier in the north.
Wholly funded by the government, the project has suffered a series of delays as a result of the increased scope of work and delay in payments.
When completed, the road will have four footbridges, bicycle lanes and pedestrian walkways, as well as several lay-bys along the service roads, especially for commercial motorists to load and offload passengers.
The works also include street lighting, the provision of road furniture (road line markings and road signs) and a weighbridge station at Dobro, near Nsawam.
Mr Lotsu was optimistic of the works, estimated to cost GH¢31,307,27, being completed in less than three months.
“We are receiving regular payments from the government now and we are happy about it,” the Project Manger, Mr Huang Song, said in an interview with the Daily Graphic.
Mr Huang expressed the hope that the payments would continue to be regular even as the projects neared completion.
He said the contractor was currently fighting for space with wood market activities and pleaded that those activities be removed immediately to ensure that work moved on as planned.
He consequently appealed to the Ga West Municipal Assembly to relocate the wood markets at Moose and Ofankor to pave way for work to progress.
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Some vendors in Ellembelle reject ¢0.20 coins for business transactions
5 minutes -
Release of GH¢5m to MMDAs in 2025 is unprecedented – Local Gov’t Minister
8 minutes -
Chiefs deserve better compensation for their role in development – Local Gov’t Minister
11 minutes -
Rebel Wilson’s claims against actress are ‘malicious concoctions’, Australian court hears
11 minutes -
President Mahama warns against interference in public sector discipline
12 minutes -
OSP lacks independent prosecutorial power – Deputy Attorney-General insists
16 minutes -
Parliament Accounts Officer linked to over GH¢139k payroll irregularity
20 minutes -
Ghana’s democracy under attack; free speech sacrificed under Mahama gov’t – Bawumia
20 minutes -
‘Power is transient’ – Otumfuo warns against political interference in chieftaincy
23 minutes -
AG’s department to await Supreme Court verdict before acting on OSP cases – Srem-Sai
29 minutes -
Srem-Sai urges Ghana to learn from other jurisdictions in OSP–AG dispute
35 minutes -
Ellembelle MP refurbishes Azulenloanu clinic with roofing sheets
37 minutes -
Akonta Mining: Court gives Wontumi last chance to file his witness statement
40 minutes -
FarmMate, MoFA sign PPP agreement to boost tomato self-sufficiency
41 minutes -
Illegal miner in alleged murder case remanded
41 minutes