President Nana Akufo-Addo has commissioned the Pokuase Bulk Supply Point, a 330/34.5 kilo-volt substation designed to improve the supply and distribution of electricity for consumers in the northern areas of Accra.
Funded by the Millennium Challenge Corporation (MCC) to the tune of $47 million, the Supply Point, according to the President, is testimony to Government’s commitment to improving the electricity supply in the country.
Commissioning the project on Wednesday, the President stated that the Pokuase Bulk Supply Point, whose construction commenced in February 2019, “is also the fourth Bulk Supply Point in Accra, it is the first 330kV Bulk Supply Point in the capital, and it is the most technologically advanced substation in Ghana”.

Siting of the BSP in Pokuase, he explained, was informed by the rapidly increasing load demand for electricity from this part of Accra, as Pokuase and its environs have become load points for power demand.
“The essence of constructing the sub-station is to improve power supply quality and reliability to some 350,000 existing customers of the Electricity Company of Ghana (ECG) in Pokuase, Kwabenya, Legon, Nsawam and neighbouring communities,” he said.
President Akufo-Addo continued, “It is also planned to reduce significantly technical losses in the Ghana Grid Company’s (GRIDCo) transmission system and the ECG power distribution system, ultimately contributing to improving their financial viability.”

Beyond the Pokuase Bulk Supply Point, the President stated that Government is carrying out several other initiatives and projects to ensure that the country is able to meet its increasing power needs, arising out of the country’s growing population and Government’s industrial agenda, through initiatives such as the One-District-One-Factory policy, amongst others.
Besides the Pokuase substation, which was commissioned, work is also ongoing on the Kasoa Bulk Supply Point, which will be the second-largest bulk supply point in Ghana.
Once completed, he indicated that the project will address low voltage and frequent power outage challenges caused by increasing domestic and industrial demand in Kasoa, Senya Beraku, Bawjiase and Nyanyanu.

“The $50 million BSP project, again, funded by the Millennium Challenge Corporation under the Ghana Power Compact Programme, will benefit some 241,508 ECG customers, and contribute to a substantial reduction in transmission losses in GRIDCo’s transmission system. The Kasoa project is expected to be completed before the end of this year,” the President added.
Further, he told the gathering that the national transmission backbone, under construction from the coast to Bolgatanga, had a gap between Kumasi and Kintampo, which has since been completed a few weeks ago.
“Completion of this portion of the Kumasi/Bolgatanga transmission line project will ease the load on Kumasi sub-stations, and become the instrument of power transmission within the Ashanti, Ahafo, Bono and Bono East Regions, and in parts of northern Ghana. In addition to this is the ongoing Tema to Accra transmission line upgrade project to accommodate an increase from 61KV capacity to 330KV capacity,” he added.
President Akufo-Addo thanked the Millennium Challenge Corporation and the United States government for their continued support; MiDA for its effective oversight of the project; Elecnor S.A., the main contractors for the procurement, supply, construction, installation, testing and commissioning of the project; as well as management and staff of GRIDCO and ECG.

He also thanked the Minister for Energy, Dr Matthew Opoku Prempeh, and his predecessors for their leadership in helping to deliver this project.
President Akufo-Addo stated in conclusion that, “government remains fully committed to ensuring safe, stable and affordable power supply in this country. As we focus on realising the Ghana Beyond Aid agenda, which has industrialisation as its crown jewel, it is imperative that we pursue this goal with dogged determination, to help ensure that every nook and cranny of this country has access to electricity as the main driver of our vision”.
Latest Stories
-
ECG to cut power in parts of Accra West on February 11 for planned maintenance
2 hours -
BoG announces guidelines to govern foreign exchange spot interventions
3 hours -
Intelligence report uncovers weapons transfers under Sudanese Army oversight to South Kordofan
3 hours -
119 people died during mediation efforts in Bawku conflict – Mahama
3 hours -
Trade Ministry to lead raw material expansion for 24-hour production, youth jobs & exports
3 hours -
Migration induced by coastal erosion: The Shama experience
3 hours -
Ghana’s economy to expand by 5.67% in 2026
3 hours -
A/R: ECG surcharges over 2,200 customers for illegal connections, recovers over GH¢4.3bn in 2025
3 hours -
With galamsey still ongoing, who is buying the gold? – Oppong Nkrumah questions gov’t
3 hours -
Avoiding Fiscal Risks in GCR’s deal with GoldBod
3 hours -
Suame Interchange won’t affect NPP votes in Ashanti – Asenso-Boakye
4 hours -
Mahama receives Transition Committee report on UGMC transfer to University of Ghana
4 hours -
Quiz Talk National STEM Programme instituted to boost innovation in basic schools
4 hours -
Unemployed graduates with disabilities engage Gender Minister on jobs and inclusion
4 hours -
Parliament approves GH¢2.9bn for Ghana Medical Trust Fund
4 hours