The Electricity Company of Ghana (ECG) says it has invested more than US$408 million in the last three years to improve electricity supply and customer service, and is now asking the Public Utilities Regulatory Commission (PURC) to approve a new tariff that will help sustain these gains.
The company proposes increasing its Distribution Service Charge (DSC1) from GHp19.0384 to GHp61.8028 per kilowatt-hour between 2025 and 2029, adding that the increase is needed because the Ghana cedi has lost about 74% of its value since 2022, reducing the company’s revenue in dollar terms by almost half.
The Distribution Service Charge 1(DSC1) is the portion of the electricity tariff allocated to ECG for its electricity distribution and retail services.
“Back in 2022, what we charged was equal to 2.27 US cents per kilowatt-hour. Today, it is worth only 1.23 cents. This makes it difficult for ECG to maintain and expand the network without upward tariff adjustments,” said Dr. Charles Nii Ayiku, General Manager for External Communications at ECG.
- slot pulsa
- situs slot 5000
- slot deposit 5000
- royalhoki77
- https://poolsafetygroup.com.au/what-we-do/
- https://patorama.com.au/helicopter-photography/
- https://reactmaintenancegroup.com.au/electrical-maintenance/
- https://www.100plumbing.com.au/work-with-us/
- slot maxwin
- https://finishingblade.ca/Banner/
- https://tubulousaustralia.com.au/gallery/
He added that the proposed percentage increase in electricity bills or the new Average End User Tariff (AEUT) is about 24 percent which is different from the DSC1. So the average end-user tariff is 24%.
He added that the new tariff will help ECG recover the cost of its recent investments, including new substations in Bibiani, Obuasi, Koforidua, and Afari; the installation of over one million smart meters; and upgrades to digital systems such as the ECG Power App, which allows customers to pay bills, buy credit, and make complaints online.
Customers, he assured, will directly benefit through system reliability and stability, improved voltage, faster response times, and more convenience. ECG projects that by 2029, average outage hours will fall by 41% and system losses will reduce from 27% to 22%.
“We are determined to build a stronger ECG that can deliver reliable service without depending on government bailouts. The proposed tariff is essential to achieving that goal,” Dr. Ayiku said.
ECG emphasised that with PURC’s oversight, the company will ensure transparency and accountability in the use of customer funds, reinvesting them into projects that improve power supply for homes and businesses across Ghana.
Latest Stories
-
Supreme Court at 150: Prof. Bondzi-Simpson traces evolution of Ghana’s judiciary from colonial era to constitutional democracy
10 minutes -
Gov’t has spent more on flood control under GARID in 2 years than NPP did in 5 – Atta Issah
13 minutes -
Prof. Bondzi-Simpson calls for deeper reflection on 150 years of Ghana’s judicial evolution
15 minutes -
MUSIGA sympathises with flood victims, urges Ghanaians to stay safe
26 minutes -
AMA declares one-month free refuse collection exercise in Accra
1 hour -
Mahama swears in Dr Pamela Graham as Ghana’s first female Auditor-General
1 hour -
Government launches dedicated GETFund support for learners with special educational needs
1 hour -
Dangerous US heatwave looms over 4 July holiday, World Cup and Swift wedding
1 hour -
Ghana Armed Forces to brief nation on nationwide flood mitigation exercise
1 hour -
Police arrest 24 in major anti-crime swoop in Ashanti Region
2 hours -
Ghana National Council of Metropolitan Chicago launches GhanaFest® 2026 with historic first-ever Ghana flag-raising ceremony
2 hours -
Public health officers push for face masks and handwashing amid post-flood risks
2 hours -
USTED, KNUST Host SFA Foundation team for NEPS Youth Mental Health Project review
2 hours -
De-emphasise “MahamaCares” nickname of Ghana Medical Trust Fund to avoid politicisation – National House of Chiefs
2 hours -
Ghana must consider evacuation policy for citizens in distress abroad — Jinapor
2 hours