Minister for Government Communication Felix Kwakye Ofosu has revealed significant procurement violations in the execution of the National Cathedral project, particularly involving Sir David Adjaye and his architectural firm.
Speaking at a press conference on Friday, July 18, at the Jubilee House, Felix Kwakye-Ofosu provided detailed updates from the government-commissioned audit report.
The minister explained that the audit uncovered major flaws in the contracting and payment processes surrounding Sir David Adjaye & Associates, who served as Lead Consultant for the project.
“Between 26th September 2018 and 7th June 2019, a total of GHS 15,738,750 was paid to Sir David Adjaye well before the formal agreement was signed on 20th August 2019,” Kwakye Ofosu stated.
He pointed out that this payment was made without prior approval of the contract sum by the Public Procurement Authority (PPA), which was later fixed at GHS 5,850,000. “This payment also preceded the approval of the contract sum of GHS 5,850,000 by the Public Procurement Authority, raising red flags about non-compliance with established procurement protocols,” he added.
The minister emphasised that the engagement of Adjaye’s firm through sole sourcing lacked the required justification and approval, stating that, “These actions represent a clear breach of procurement procedures as outlined in Section 40(1) and (2) of the Public Procurement Act, 2003 (Act 663), as amended by Act 914, and raise serious concerns about transparency, value for money, and adherence to due process in the award and execution of public contracts.”
He continued by highlighting other areas of concern, including unexplained payment components. “Portions of the total contract value specifically the mobilisation fee of USD 1,500,000 and a Use/After Care component of USD 1,187,500 were included in the payment schedule but lack any detailed breakdown or explanation of their composition,” he said.
Further scrutiny, Kwakye Ofosu noted, revealed a troubling discrepancy in the reported mobilisation fee. “While the Office of the President confirms a payment of only USD 89,000, a letter from Sir David Adjaye & Associates dated 13th August 2020 states that USD 950,000 was received as mobilisation a gap that requires urgent clarification,” he explained.
The minister also addressed variation orders for additional design work executed by Adjaye’s firm. “David Adjaye is reported to have undertaken extra work estimated at USD 12,430,221 under Variation Orders 1, 2, and 3,” he said.
“These include major design changes such as a 350-seater restaurant, a museum extension, and a Bible museum.”
However, he stressed that none of these additions were formally captured in the original signed contract. “These additions were not captured in the original signed contract, indicating a failure to formally regularise significant scope changes before making payments regarding these changes,” he added.
Latest Stories
-
Discussions on petroleum taxes review ongoing with Finance Minister – Jinapor
6 minutes -
BMW Club Ghana partners National Road Safety Commission for “Stay Alive” Easter road safety campaign
11 minutes -
Health Ministry launches World Health Day 2026, urges science-based action
26 minutes -
MMFL anchors MTN Group’s fintech push in Ghana
35 minutes -
Ghana’s economy shows recovery signs, but risks persist – S&P maintains stable outlook
51 minutes -
SWAG commemorates its 8th anniversary with a public lecture
54 minutes -
Ibrahim Mahama claims Police Commander failed to stop alleged assault
57 minutes -
Damang lease award to E&P followed due process — Minerals Commission
1 hour -
Today’s Front pages: Wednesday, April 8, 2026
1 hour -
Julian Opuni reaffirms Fidelity Bank support for industry-led skills training at DTI Berekuso campus
1 hour -
CAF President arrives in Dakar to meet Senegalese President, football authorities over AFCON title saga
1 hour -
Pastor arrested over viral threats against Vice-President
1 hour -
2026 Success Africa Summit: MTN’s Adwoa Wiafe challenges youth to act with purpose, not just pursue titles
1 hour -
Nurse laureate launches Cancer Care Africa Foundation to tackle late diagnosis, workforce gaps
2 hours -
Ghana to lose GH¢18.15bn in revenue by 2027 from abolishing Covid levy, E-levy – CPS study
3 hours