Members of the Public Accounts Committee (PAC) of Parliament have expressed shock that a contract awarded Yiadom Builders Limited for the continuation of the Sakomono Coastal Protection Project had been renewed against its recommendation.
The contractor has completed only 10 percent of the 600- meter sea protection project awarded in 2004 that was expected to be completed within five months.
Mr Samuel Sallas-Mensah, Chairman of the PAC who led the Committee to inspect ongoing government projects in the Tema Metropolis on Tuesday, said committee members were surprised that the Ministry of Works, Housing and Water Resources, had renewed the contract after the committee, Parliament and Mr Hackman Owusu-Agyeman, former Minister of Water Resource, Works and Housing had recommended that the contract should be terminated and the mobilization fee refunded by the contractors.
Mr Mensah, Member of Parliament for Upper West Akyem, said instead of terminating the contract, the ministry ordered a revaluation leading to the appreciation of the total cost of the contract, GH¢660 million, by GH¢260 million.
Mr Enoch Teye Mensah, Member of Parliament for Ningo/Prampram, said he was shocked and annoyed at the work done so far adding that the contractor did not deliver on their promise.
Mr Hubert Osei-Wusuansa, Project Engineer who conducted the committee members round, said the contractor abandoned the project after receiving the mobilization fee and that they failed to deliver even after the extension of the five months to 10 months.
Mr Osei-Wusuansa said the contractor was given the contract because they had the equipment and staff.
At Community 18, Lashibi, Mr Wise Ametepey, Head of Drainage of the Hydrological Service Department, led the committee to inspect a GH¢160 million drainage expansion project.
Mr Ametepey said the first phase of the project, which started in 2004, had been completed but the second phase has not started due to lack of funds.
He said the project was designed to widen and deepen the drainage to collect flood waters from Communities 18, 19 and 20 into the Sakumo Lagoon.
Mr Ametepey said 3.5 kilometers stretch of the drainage with six culverts were completed last year and that though the project was not fully completed, flooding in the three communities had been minimised.
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Mahama calls for prosperity, peace and progress in New Year Message
1 hour -
Côte d’Ivoire stun Gabon with last-minute 3–2 thriller to top Group F
3 hours -
Ho zongo community slams REGSEC over two-week mosque closure
4 hours -
Tema police foil armed robbery attempt at Afienya; Four suspects killed
4 hours -
Two dead, two in custody over fatal family land feud
5 hours -
Anthony Joshua discharged from hospital after fatal road crash
5 hours -
Trump media firm to issue new cryptocurrency to shareholders
5 hours -
Ebo Noah arrested over failed Christmas apocalypse and public panic
7 hours -
‘Ghana’s democracy must never be sacrificed for short-term politics’ – Bawumia
7 hours -
Bawumia congratulates Mahama but warns he “cannot afford to fail Ghanaians”
7 hours -
CICM backs BoG’s microfinance sector reform programme; New Year Debt Recovery School comes off January-February 2026
7 hours -
GIPC Boss urges diaspora to invest remittances into productive ventures
7 hours -
Cedi ends 2025 as 4th best performing currency in Africa
7 hours -
Fifi Kwetey brands calls for Mahama third term as ‘sycophancy’
7 hours -
Bawumia calls for NPP unity ahead of 2028 elections
8 hours