The Testing and Commissioning phase of the Ghana Gas-West African Pipeline Company Limited (WAPCo) Interconnection Project is almost completed.
This follows successful completion of engineering and construction work on gas pipelines from Sanzule through to the Takoradi Regulatory and Metering System (TRMS) of the Volta River Authority at Aboadze.
Head of Communication at Ghana National Gas Company Limited, Ernest Owusu Bempah, during an inspection visit of the project site on Monday said, the exercise involves some protocol that needed to be adhered to so as to ensure the safety and efficiency of the pipeline system.
“They need to check the pressure, understand how the flow is going to be like, detect any possible leakages, technically to make sure that everything is fine before they start pushing the gas,” he stated.
Mr Owusu Bempah disclosed that the company is currently producing about 37million metric cubic feet of gas to the Volta River Authority for the testing and commissioning phase of the pipelines.
The success of testing would enable them to roll out fully the production and supply of gas through the TRMS to the Eastern enclave to power up thermal plants.
“At the moment we doing about 37 million cubic feet on the pressure within the testing and commissioning, from there it can take about 60 million cubic feet of gas; which is very significant as it can do about 300 megawatts of electricity” he added.
He is highly optimistic that the recurring gas shortage, which in the past hit power-producing plants in the country will be extinguished.
“…there’s not going to be any problem when WAPCo tells us there’s not enough gas available. There will be more gas flowing…we will be doing about 30 to 60 million cubic feet of gas to help us generate electricity,” he elaborated.
The Officer-in-charge of Pipeline and Station at the TRMS, Emmanuel Ackon clarified that the testing and commissioning phase of the project begun on Thursday, May 16.
According to Mr. Ackon said should things go according to plan, the exercise he described as “far excellent”, would be completed in the next couple of days.
“They need to check the pressure, understand how the flow is going to be like, detect any possible leakages, technically to make sure that everything is fine before they start pushing the gas,” he stated.
Mr Owusu Bempah disclosed that the company is currently producing about 37million metric cubic feet of gas to the Volta River Authority for the testing and commissioning phase of the pipelines.
The success of testing would enable them to roll out fully the production and supply of gas through the TRMS to the Eastern enclave to power up thermal plants.
“At the moment we doing about 37 million cubic feet on the pressure within the testing and commissioning, from there it can take about 60 million cubic feet of gas; which is very significant as it can do about 300 megawatts of electricity” he added.
He is highly optimistic that the recurring gas shortage, which in the past hit power-producing plants in the country will be extinguished.
“…there’s not going to be any problem when WAPCo tells us there’s not enough gas available. There will be more gas flowing…we will be doing about 30 to 60 million cubic feet of gas to help us generate electricity,” he elaborated.
The Officer-in-charge of Pipeline and Station at the TRMS, Emmanuel Ackon clarified that the testing and commissioning phase of the project begun on Thursday, May 16.
According to Mr. Ackon said should things go according to plan, the exercise he described as “far excellent”, would be completed in the next couple of days.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
FBI searches home of Washington Post reporter in classified documents probe
17 minutes -
Ghana’s Benjamin Arhin shines on Internacional debut with Man of the Match display
40 minutes -
Stanbic Bank Ghana maintain top rank in Customer Experience Leadership in 2025 KPMG Assessment
48 minutes -
Newmont-backed AI smart lab powers Kona D/A students to victory at Ghana Robotics Competition
1 hour -
Venezuelan acting president says hundreds of prisoners have been released since December
1 hour -
Nilex Suites holds first open house ahead of official launch
2 hours -
We’re far from Ofori-Atta’s extradition – Frank Davies responds to Ablakwa
2 hours -
Judicial Service, Finance Ministry summoned ahead of JUSAG strike
3 hours -
Takoradi Port to receive largest bulk carrier ever to berth in West Africa
3 hours -
Mane hits winner as Senegal end Salah’s Afcon bid
3 hours -
NLC summons Finance ministry, Judicial service over JUSAG’s 8-month salary arrears
3 hours -
Interior and Education Ministries signs MoU to produce sanitary pads, school uniforms and furniture
3 hours -
GIS to repatriate 8 foreign nationals convicted over illegal activities under guise of QNET
3 hours -
The Republic of Queues: DVLA’s Digital Revolution
3 hours -
ACEP hosts Guinea delegation for three-day peer learning exchange on civil society advocacy
3 hours