Construction work on the Tamale Interchange is progressing steadily to ensure its completion by the end of February, Mr Emmanuel Degbotse, Resident Engineer, has said.
“The project is 95 percent complete. What is left is five percent and we are working day and night to make sure that everything is completed on time,” he said.
Mr. Degbotse said what remained to be done included the asphalting and street lighting as well as reconstruction of drains at the down stretch of the project.
He gave the update when Mr. Kwasi Amoako-Attah, the Minister of Roads and Highways, accompanied by Alhaji Shani Alhassan Saibu, the Northern Regional Minister, inspected construction works on the road.
Mr. Amoako-Attah, having been briefed about the progress of work, announced that the project would be ready for commissioning by the end of March.
"The contractor has assured me that every work associated with the Interchange will be completed by end of February and that the first two weeks of March will be used to do the end finishing and then anytime from mid-March the President will commission it,” he said.
Work on the Tamale Interchange, which began in 2019, is being executed as part of the $2 billion China Synohydro deal to, among other things, enhance traffic flow in the Northern Regional capital.
Other road projects the Minister and his team inspected in Tamale and the Sagnarigu Municipality included the Tamale Industrial Area Road linking the Nyohini Roundabout, which has been fixed and opened to traffic, and the Fuo Road.
Mr Amoako-Attah said 40 kilometers of roads had been asphalted in the area out of the 100 kilometers earmarked for asphalting.
He, therefore, urged the public, including Members of Parliament in the Northern Region, to support the electronic transaction levy (e-levy) to enable the government to raise the needed resources for more development projects.
Alhaji Saibu, on his part, said the number of road projects ongoing and completed in the region showed that the government was on course to fulfilling its promise to undertake massive road infrastructure in the country.
Latest Stories
-
NAIMOS disrupts nighttime illegal mining operations along the Ankobrah River
13 minutes -
Health Ministry adopts population-based pharmacy licensing to boost universal healthcare
15 minutes -
Ghana Publishing says recent turnaround due to current administration, not former MD
16 minutes -
We voted, now we need water and roads – Bono East residents to government
17 minutes -
Vice President lauds Local Government Ministry for driving decentralisation reforms
19 minutes -
Spatial Planning Authority proposes 90-day emergency pilot to break Accra’s gridlock
24 minutes -
WAFCON 2026: Black Queens in Group D, face Cameroon, Mali and Cape Verde
38 minutes -
NCCE urges public to prioritise importance of paying tax for development
42 minutes -
Widespread delays hit Uganda election amid internet shutdown
44 minutes -
Fear grips Akoti health centre staff after armed men storm facility
45 minutes -
Astronauts splash down to Earth after medical evacuation from space station
51 minutes -
Solutions gather dust: Spatial planner laments idle €2.4M transport blueprints amid Accra’s gridlock
51 minutes -
Abossey Okai spare parts dealers deny price hikes amid transport shortages
1 hour -
Assibey-Yeboah urges NPP to field new flagbearer, rejects Bawumia repeat bid
1 hour -
Ohwimase residents threaten mass demo over deplorable roads
1 hour