Barring any technical hitches, residents of Accra East would have water supply restored on Thursday after a 10-day water interruption in some parts of Accra necessitated by expansion works to boost the quantity of water supply to the area.
The Ghana Water Company Limited (GWCL) on Tuesday August 26 shut down the pumps at its East Accra booster station to increase the capacity of the pumps to supply more water.
Mr. Samuel Kodwo Yeboah, Station Manager of the Accra booster station, announced this when the Chairman of the Public Utilities Regulatory Commission, Professor Kwabena Frimpong Boateng, and some commissioners visited the project site to assess the extent of work.
The three-prong project aims to increase the amount of water pumped at Weija by 50 million gallons, installed new pipe lines to Accra Resevoir and a panel to enhance flow of electricity.
Mr. Yebaoh said at the end of the project, communities in eastern Accra, including Adenta, Madina, Pantang, University of Ghana, GIMPA and surrounding areas would experience an enhanced water supply when work to link the pipes from the Weija Dam to the Accra Booster Station at Okponglo was completed.
The project dubbed: "East-West Interconnection Project," would make it possible to link water supply from the Weija Dam to the Accra Booster Station so that excess water from Weija could be channelled to the eastern parts which do not have constant water supply.
Water from the Kpong Dam and Weija will be connected in a way that would make Wieja supplement supplies from Kpong. As part of the project GWCL is replacing the old pumps at the booster station.
The old pumps, which currently have the capacity to pump about 130,000 gallons of water per hour, would be replaced with new ones, which have higher capacity to pump about 260,000 gallons of water per hour.
Prof. Frimpong Boateng said he was impressed with the level of work, especially the support of the Electricity Company of Ghana in providing two dedicated lines to the booster station to ensure constant water supply.
He expressed the hope that on completion of the project, water supply to the eastern part of Accra would be improved.
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Parliament passes Education Regulatory Bodies Amendment Bill, 2026
10 minutes -
Chief Justice declares ADR Week nationwide
10 minutes -
Four million Ghanaians living with silent kidney disease — Experts say
16 minutes -
Jessie Buckley, Michael B Jordan and One Battle After Another reign at Oscars
22 minutes -
African nations tiptoe around recruitment of citizens by Russian networks
34 minutes -
Oscars 2026: Winners list in full
43 minutes -
Madagascar anti-corruption chief Rajaonarison named prime minister
55 minutes -
Indian foreign minister hails talks with Iran to open Strait of Hormuz, FT reports
1 hour -
Africa-bound India-flagged fuel tanker sets sail from east of Hormuz, Indian official says
1 hour -
How Iranians are evading internet blocks to contact family abroad
1 hour -
South Africa’s president authorises deployment of 2,200 troops to help fight crime
2 hours -
Israeli forces kill Palestinian couple and two of their children in occupied West Bank
2 hours -
Two die including uni student in meningitis outbreak
2 hours -
Severe flooding kills 66 in Kenya, as heavy rains continue
2 hours -
Is Dubai’s glossy image under threat? Not everyone thinks so
2 hours