Audio By Carbonatix
The Ministry of Roads and Highways has explained that the delay in completing the Ofankor-Nsawam road project, a key stretch connecting the national capital, Accra, to the Eastern and the Ashanti regions, is due to some ongoing court cases that have hindered construction efforts.
Initially scheduled for completion in July 2024, the project now faces an indefinite delay due to unresolved legal disputes that have significantly slowed progress.
In an interview with Accra-based Channel One TV on Monday, February 17, the Ministry’s Public Relations Officer (PRO), Nasir Ahmad Yartey, disclosed that legal challenges have impeded the contractor’s work, preventing progress on key construction aspects until the court cases are resolved.
“The primary challenge with the Ofankor-Nsawam road project is related to court cases. Last year, we had over 100 cases associated with the project, and we’ve managed to clear about 20 of them. As it stands, there are approximately 80 unresolved cases between Amasaman and Nsawam. These court cases prevent the contractor from having the right of way to continue their work,” he explained.
Mr Yartey noted that many of the disputes stem from property owners contesting demolitions or seeking compensation, which has prolonged the legal impasse and stalled the project.
“We cannot take the law into our own hands. If demolition of a property is required but the owner is litigating the matter in court, there is little we can do,” he added.
The $350 million Ofankor-Nsawam road project is a vital infrastructure initiative aimed at improving transportation along the Accra-Kumasi highway, one of Ghana’s busiest road networks.
The road expansion and rehabilitation are expected to alleviate traffic congestion, boost trade and commerce, and provide safer, more efficient transportation for commuters.
However, many residents and commuters who rely on the road daily have voiced frustration over the delays, citing worsening traffic conditions and the accompanying economic and social challenges.
Numerous individuals have urged the government to expedite the resolution of the court cases to allow construction to resume in full.
Latest Stories
-
GPL 2025/26: Asante Kotoko draw with GoldStars to extend winless run
2 hours -
Fire guts temporary wooden structures at Afful Nkwanta in the Ashanti Region
3 hours -
Haruna Iddrisu didn’t approve gender identity content – Education Ministry
3 hours -
‘We are not for sale’: Thousands rally in Greenland and Denmark against Trump’s annexation threat
3 hours -
Deputy Education Minister directs GES to act on video of SHS students displaying charms
3 hours -
From camouflage to tracksuits – Guinea’s junta leader becomes civilian president
3 hours -
Iran supreme leader admits thousands killed during recent protests
4 hours -
Judiciary to roll out court decongestion measures, galamsey courts – Chief Justice
5 hours -
Ugandan leader to extend 40-year rule after being declared winner of contested poll
5 hours -
Residents demand action on abandoned Salaga–Kumdi–Kpandai road
6 hours -
Ghana, Japan explore ways to deepen long-standing bilateral ties
6 hours -
Ghana Navy foils illegal fuel bunkering operation along Volta coastline
6 hours -
Gov’t assures minimal power disruption during WAPCo gas pipeline maintenance
6 hours -
Burna Boy and Sporty Group unveil new single “For Everybody” celebrating Africa’s sports heritage and cultural excellence
7 hours -
Achieve By Petra partners Richie Mensah to drive financial independence
7 hours