A Joy News Hotline Documentary has revealed that some school projects, estimated to cost ¢21 million of oil revenue, remain largely undone and abandoned.
In the Ashanti region, a teaching hospital administration block, a project to address a large number of admissions into the Kwame Nkrumah University of Science and Technology (KNUST) School of Medical Sciences, has been abandoned after eight years.
The project originally estimated to be ¢6 million and later revised to about ¢18 million due to delays in completion, now costs ¢21 million.
Aside that is the Apedwa SDA Primary School. The six-unit Classroom Block in the East Akim District is almost sinking after the government invested ¢130,000 petroleum revenue into its construction.
The gaping holes in the library block are obvious. This is life-threatening to both students and their teachers.
That is not all.
In 2011, the government awarded a contract worth over GH₵58,000 for additional classroom facilities for the Apenkro JHS in the Atwima Mponua district of Ashanti region.
Even though the building is yet to be completed, portions of it have developed cracks.
Assistant Head Master of the School, Amoako Sarpong George is worried about the slow pace of work.
Faustina Owusua, a pupil, laments on how students are sometimes attacked by snakes and lizards during lessons because classrooms have no doors and windows.
According to the school authorities, the project has stalled because government has not paid the contracted, a claim they attribute to the contractor.
The situation is no different from the Begoro Senior High School in the Eastern region.
In 2010, Moferg Company Limited was awarded a contract to rehabilitate the Science Resource Centre of the school.
The initial contract sum for the project was over ¢130,000. The Regional A.E.S.L. Consultant, Frimpong Gyamfi told the Public Interest and Accountability Committee that government has issued a certificate of payment of ¢52,765 to the contractor. This was on April 9, 2013.
The contract was expected to have been completed in four months. But, nine years on what is visible is a pale structure with no windows and doors.
Headmaster of Begoro Senior High School, Daniel Mensah reveals, the contractor abandoned the site after starting initial terrazzo works on the building.
Now Science education in the school is dead. Science experiment kits are now gathering dust in the school’s washroom.
They are appealing to government to urgently intervene to get the project completed.
In the Northern region, school authorities at the Bagabaga College of Education are facing a similar ordeal.
The low voltage of the school’s power source compelled government to award an upgrading of an electrical power supply contract in 2013 to the Jondee Electricals. It was worth ¢248, 245.
But, at the time of going to press the transformer which was meant to be installed to step up the voltage supplied to the College of Education is sitting at the administrative block of the institution while the school suffers.
Joy News Kwetey Nartey concludes that in all his tour across the country, he didn’t come across a project funded with the oil money where the people were impressed with the value for money.
Chairman of Public Interest Accountability Committee (PIAC), Dr. Steve Manteaw, believes more needs to be done.
According to an inspection report by the PIAC, over 50% of school projects funded by oil money show signs of serious deterioration in less than three years after completion.
The resultant effects have been more suffering for the ordinary people for whose purpose the Petroleum Management Act was passed.
According to this Act, up to 70 percent of oil proceeds go into the national budget.
The law further directs that these funds should be channeled to development in key sectors such as education, health and water infrastructure, among others.
But, a 2017 Project Inspections Report by PIAC revealed that 50% of all oil-funded projects in three regions – Upper East, Upper West and Northern – are now ghosts projects.
According to the 2015 Ghana Poverty Mapping report, these areas have the highest poverty rate. Poverty incidence is pegged at 70 percent in this part of the country.
Latest Stories
-
Iran World Cup players granted visas to enter the US, says White House official
2 hours -
Now that kidnapping has become an industry…, by Adekunle Adekoya
2 hours -
Old students’ association breaks silence over Kumasi Academy arson threats
2 hours -
Suspect to be arraigned on June 8 – GHS condemns midwife assault
3 hours -
Firefighters cut through mangled taxicab to save trapped passenger after STC bus crash
3 hours -
Mona Montrage, 31 other Ghanaians named in US ‘Worst of the Worst’ arrested criminal list
4 hours -
Kumasi to go dry for 48 hours as Barekese Water Treatment Plant shuts down for critical repairs
4 hours -
Democracy without Dividends? Governance expert warns citizen apathy could endanger Ghana’s democratic future
4 hours -
Annual Flooding and Piss-Poor Leadership
5 hours -
Attack on Community 22 Polyclinic midwife sparks renewed call for safety at health facilities
5 hours -
Abu Jinapor accuses gov’t of diluting anti-LGBTQ bill, calls for assent to original 2024 version
5 hours -
Teachers suspend strike over assault after assurances from Western Regional Minister
6 hours -
US military says it struck Iranian drones and radar sites
6 hours -
Where is the GH¢25.3 million difference? NPP fires questions at Finance Ministry
7 hours -
The cash-in-the-sofa saga that just won’t go away for South Africa’s president
7 hours