The Performance Audit Report on Capital Projects funded through District Development Facilities in 30 Districts Assemblies compiled by the Auditor-General has uncovered cases of payment for no work done.
Findings of the Audit Report on payment and work done showed that monies were disbursed for non-executed works resulting in overpayments.
“For example, the pavement for work at the taxi station of Ho barracks was paid in full when only 50 per cent of the work was done.
In some instances, items that were specified for installation were omitted yet payments were made like the U drain around the Bibiani District Police Headquarters, which was not done yet paid in full,” it noted.
The report said in Prestea Huni Valley, the specified depth of the borehole at Gordon Community was 35 to 45 metres for a Mechanised pump however investigations revealed that the depth was not up to that.
“Upon completion of the drilling, an AFRIDEV hand pump recommended for a depth of 16.6 to 30 metres was installed and therefore was not deep enough to pump out water from below 35meter when it was completed and handed over,” it said.
The report said the contractor was paid in full for a mechanised borehole when he provided a manual hand pump borehole and the community had no water.
“We observed that Assemblies make payment for no work done due to insufficient due diligence and familiarisation. In the individual reports, we have recommend for disallowance and Surcharge of the individuals concerned,” it stressed.
The report stated that the occurrences were due to a combination of lack of due diligence on the part of the District Management Team, District Works Engineer (DMEs) and familiarization between DWEs and Contractors.
It said, “Contractors and works engineers get to familiarize with each other to the extent that a suggestion by a contractor for DWE to increase the work done beyond the actual work to cater for delayed payments are accepted and paid for.”
The report said payment for work done except for mobilization was based on measured work at the time of preparing Interim Payment Certificate (IPC).
It noted that the DWEs, upon request by contractors measure the amount of work done, cost it, and prepare certificates to cover the amount.
Per the rule, it said the DMT validates the work against the IPC quantities before approval was given for payment.
Latest Stories
-
Briton among 19 killed in Nepal bus crash
2 minutes -
IMANI Brief: The MP’s Share of the DACF a legal overreach and must stop
5 minutes -
Artificial Intelligence: Africa gov’ts must adopt, adapt, and indigenise, but don’t copy and paste
13 minutes -
CalBank delivers strong capital rebound in 2025 as profit-before-tax hits GH¢ 481.4m
16 minutes -
COCOBOD’s statutory monopoly/criminalised single-buyer system (Part I)
20 minutes -
Kotoka International Airport renamed Accra International Airport
31 minutes -
Minority raises alarm over delayed rent allowances to Ghana Prisons Service officers
33 minutes -
No ‘dumsor’ in Ashanti Region – ECG assures residents
37 minutes -
Beyond certificates: Why Ghana’s TVET revolution must prioritise employment over enrolment
42 minutes -
Miss Intercontinental Ghana winner sues organisers after title withdrawal
56 minutes -
Bioko has truly redefined my appreciation of locally made chocolate and the power of a woman’s vision
59 minutes -
Ghana moves to open key public offices to dual citizens in historic constitutional review
1 hour -
Punishment alone won’t solve student behaviour, moral guidance needed – Irene Sam
1 hour -
UK launches eVisas for Nigerians as US expands short-term travel access in Ghana
1 hour -
Viral fame vs traditional education in the republic of uncommon sense
2 hours