Ghana’s 24-hour economy policy aims to transform the nation into a round-the-clock hub for industry, commerce, and services, boosting productivity and economic growth. However, this ambitious vision depends on reliable and sustainable electricity supply.
The feasibility of the program depends on electricity demand and supply, as the policy is a manufacturing-led initiative involving agro-processing and industrial parks across the country. Therefore, it is essential to assess energy needs against supply.
This assessment uses two scenarios: Business as Usual (BAU) and the 24-Hour Economy Policy.
The baseline total energy demand for 2025, as indicated by the Energy Commission, is likely 25,836 GWh, with a peak demand of 4,125 MW. Against this, Ghana’s installed capacity stands at 5,260 MW, with a dependable capacity of 4,856 MW, reflecting a reserve margin of about 18%.
Under the BAU scenario, demand will peak at 6,150 MW by 2030, implying an average annual peak demand increase of 405 MW from 2025.
Based on this projection, Ghana will exhaust its dependable capacity by 2027 and its installed capacity by 2028. Without new investments in power generation, Ghana could face Dumsor (power outages) by 2028, even without the 24-hour economy policy.
The 24-hour economy policy introduces new infrastructure demands, including 50 industrial parks (e.g., Kumasi Machinery Park, Legon Pharma Park), agro-ecological zones, and digital hubs as well as behavioral change (Night shift). Successful implementation in the medium to long term depends on stable baseload supply or off-grid renewable solutions.
If current peak demand issues are not addressed, the policy’s sustainability will be at risk. Factoring in the policy’s impact, Ghana’s peak demand by 2030 would rise to 9,150 MW, with an average annual increase of 600 MW. To sustain the policy, Ghana must increase power generation by at least 1,200 MW by 2027.
This additional capacity would support: 20 agro-industrial parks (10 MW each), 40 agro-ecological zones (5 MW each), 50 digital centers (2 MW each), Night shifts and BAU demand (400 MW). Failure to secure 1,200 MW of additional power by 2027 could lead to a crisis caused by excess demand.
Expanding capacities in alignment with future demand is projected to cost about $2 billion dollars by 2027 and about $7 billion by 2030. Improving the grid (transmission and other support infrastructure) will cost about $3 billion between 2026 to 2025.
This means that by 2030, Ghana is expected to expend about $10 billion into areas of electricity expansion, improvement in grid infrastructure, developing off grid solutions and ensuring system efficiency so as to sustainable implement the policy.
Latest Stories
-
Kasoa New Market fire contained; no casualties recorded – GNFS
3 hours -
SWAG President Kwabena Yeboah celebrates 35 years of marriage
4 hours -
Naser Toure Mahama’s death a painful loss to Parliament – Richard Acheampong
4 hours -
There’s no version of my story without Kwasi Twum- Channel One TV, Citi FM MD
4 hours -
We will consolidate 2025 gains in 2026 – MIIF CEO
4 hours -
Ghana’s Growth Engine: How special economic zones (Sezs) will reshape the nations economy.
5 hours -
Fire breaks out at Kasoa New Market, firefighters battle blaze
7 hours -
Final funeral rites of late Ayawaso East MP Naser Toure Mahama set for January 5
7 hours -
GPL 2025/2026: All Blacks stun Kotoko in Swedru
8 hours -
Tamale: Police arrest 12 in New Year anti-drug operation
8 hours -
GPL 2025/26: Salim Adams second half strike earns Medeama win over Hearts
8 hours -
Kennedy Agyapong calls for unity ahead of NPP’s 2028 bid at Ken’s National Praise 2026
8 hours -
GPL 2025/26: Vision FC shock title-chasing Aduana FC in Dormaa
9 hours -
Police arrest two women over alleged assault of 12-year-old girl at La
9 hours -
GSE ends 2025 as second-best stock exchange in Africa
9 hours