The Site Manager for the reconstruction of the 66-kilometre Agona-Nkwanta to Tarkwa road in the Western Region, Peter Quarshie, has said the project is 80 per cent done and expected to be fully completed by the end of August this year.
Mr Quarshie was briefing Mr Francis Asenso-Boakye, the Minster for Roads and Highways, on the state of the road as of April when he toured major ongoing road project sites in the Western Region.
He was accompanied by the Western Regional Minister, Kwabena Okyere Darko-Mensah, officials from the Ghana Highway Authority and Department of Urban Roads, and Metropolitan, Municipal and District Chief Executives, among others.
The project, which started in 2021 at an estimated cost of 95 million Euros, is being undertaken by M/S Gabriel Couto-Rango Consortium, with funding from the Deutche Bank AG, Frankfurt, Germany.
Mr Quarshie explained that the scope of the reconstruction of the stretch included concrete works which entailed building drains, and pipe and box culverts.
Others were the application of bituminous prime coat, bituminous tack coat, asphaltic concrete binder course and asphaltic concrete wearing course.
The rest were the provision of walkways, medians, streetlights, traffic signs and markings including road line markings, information, warning and mandatory signs, and kilometre posts.
He assured the Roads and Highways Minister that the contractor would work assiduously to meet the project deadline of August 30.
Mr Asenso-Boakye expressed satisfaction at the progress on site and commended the contractor for the quality of work done so far.
He said the project, upon its completion, would facilitate socio-economic activities to enhance the living standards of the people along that corridor.
Mr Asenso-Boakye said the government would do everything in its capacity to provide good road infrastructure in other areas of the country for sustainable growth.
He went round other areas to assess progress of ongoing projects like the Sekondi to Takoradi road dualisation, and sectional repair works on Nkroful Junction–Ketan to Kojokrom Junction- Kojokrom Market Road on the main Takoradi to Cape Coast highway, which were at various stages of completion.
The rest were the proposed road construction at Mpohor, dualisation of Takoradi to Agona-Nkwanta, and Shama Junction-Shama roads.
Latest Stories
-
Ozempic maker takes rival to court over alleged fake weight-loss drugs
1 minute -
Cape Coast Sea Defence Project: We can’t go beyond completion timeline – Ken Adjei
10 minutes -
‘A Tax For Galamsey’: Security operatives aware, part of taskforce – Amansie Central Presiding Member
13 minutes -
John Awuah: Where are the CSOs in the galamsey fight?
17 minutes -
KATH compelled to detain patients over medical bills, complains of costs and resource burdens
38 minutes -
Gov’t begins construction of CATH Lab at KATH to curtail surging heart conditions
51 minutes -
High Court dismisses Gifty Oware’s application for Supreme Court referral
51 minutes -
Education Minister proposes ‘Our Day’ cultural wear in schools after Mahama’s fugu buzz
55 minutes -
Women’s FA Cup: Hasaacas draw Ampem Darkoa Ladies in quarterfinals as Jonina face Supreme Ladies
1 hour -
Ghana’s food insecurity hits 38.1% as over 13m people face hunger risks- GSS
1 hour -
Ghana holds strategic talks with Afreximbank on minerals sector development
1 hour -
Cost of Azumah Nelson Sports Complex to be revealed after audit – NYA CEO
1 hour -
Tetteh Quarshie Memorial Hospital records milestone with first dialysis procedure after 64 years
1 hour -
Cape Coast Phase II Sea Defence project advances to protect coastal communities
1 hour -
Macron urges Europe to start acting like world power
1 hour