Energy Minister Matthew Opoku Prempeh says Ghanaians should brace themselves for systematic nationwide power outages in May.
During a press briefing Thursday to discuss the country's power supply, the Energy Minister disclosed that due to ongoing works on the Pokuase and Kasoa substations, the coming month would see an increase in shortage of power supply.
Although power supply providers such as Ghana Grid Company Limited (GRIDCo) and the Electricity Company of Ghana (ECG) say there is no specific timetable for power outages, Mr Opoku Prempeh indicated that in May, power outages would be well ordered and planned.
"Just two days ago, I received a letter from the Millennium Development Authority (MiDA) who are helping to upgrade the Pokwase and Kasoa substations just two days ago, informing me that the progress of the substation is such that in the month of May, around my birthday, there is going to be systematic power outages," he said.

In view of this, Matthew Opoku Prempeh noted that GRIDCo and ECG would be brought to the discussion table to enable them "communicate to the people who will be affected way before it happens."
For the past two months, Ghanaians have expressed worry about the country heading back to the days of "dumsor."
But the Ministry of Energy has stated that the present challenges facing the energy sector would be resolved after present transmission lines are upgraded to resolve the issue of congestion.
In a press statement dated on Sunday, GRIDCo attributed Saturday evening’s power outage to the falling of a conductor on the Tema-Accra East transmission line at Trasacco.
Referencing the GRIDCo statement, the Energy Minister entreated all power supply providers to continuously update Ghanaians on recent developments to enable them to plan their daily activities smoothly.
"Ladies and gentlemen, the power system involves machines and equipment as a result, maintenance processes are scheduled in order for the machines not to break down.
"However, there are occasions where the systems experience unplanned faults which results in outages that last a while before restoration.
"It is only appropriate that managers of the power systems of Ghana communicate such reasons timeously to the public in order for people to plan their lives accordingly," he said.
Latest Stories
-
NICKSETH recognised as Best Building & Civil Engineering Company of the Year 2024/2025 by GhCCI
1 minute -
MISA Energy rebrands in Kumasi, pledges better service and sustainability
4 minutes -
Kenyasi assault case: Woman handed 15-month jail term for injuring child
2 hours -
Mahama’s trust well placed, I remain focused on fixing education – Haruna Iddrisu
3 hours -
IGP Yohuno promotes 13 senior officers in recognition of exemplary service
3 hours -
Miss Health Organisation unveils new Miss Health Africa and Ghana queens
3 hours -
Andy Dosty set to headline inaugural Ghana Independence Day celebrations in Europe
3 hours -
GoldBod rejects IMF claims of $214m losses under gold-for-reserves programme
4 hours -
Some MMDCEs reject uniform 24-Hour Economy Market model, seek flexible options
4 hours -
Government to reform cultural, creative sector policies
4 hours -
Illegal farming ravages Chai River forest reserve
4 hours -
Christmas should inspire unity and national renewal – Prof Opoku-Agyemang
4 hours -
Ashanti Region: NADMO prioritises preventive measures to reduce road carnage
4 hours -
Mahama pledges reset, growth and jobs for all Ghanaians in Christmas message
4 hours -
13 inmates at Nsawam Prison granted bail under the Justice For All Programme Â
4 hours