The board and management of the Komfo Anokye Teaching Hospital (KATH) in Kumasi have expressed worry over the continued delay in the completion of works on a sickle cell and blood center project for the hospital.
Construction works on the project, which is being sponsored by the Sickle Cell Foundation of Ghana (SCFG) with funding from the Ghana National Petroleum Corporation (GNPC), have come to a halt for more than two years.
The project was to be completed in May 2019 but had to be extended for one year to May 2020.
So far, the first fixing of the plumbing and electrical works have been completed and the building of the basement structure and ground floor has also been finished.
However, further works on the project have been aborted because the contractor had not been paid since August 2020 and at the end of the year 2021, the project was still behind schedule.
This came to light when the Chief Executive Officer of KATH, Dr Oheneba Owusu-Danso, led members of the KATH Board to visit some of the hospital projects under construction.
The visit was to allow the board members to acquaint themselves with the progress of work on the projects and the challenges facing the contractors.
Nana Asibey Opoku, Consultant to the project, told the team that since August 2020, no payment had been made to the contractors, thus accounting for the stalling of the project.
He said the Foundation had lobbied the Asantehene, Otumfuo Osei Tutu II, to press on the GNPC to release funds for the completion of the project.
The GNPC, through the Asantehene in 2016, presented a cheque for $4.5 million to the Sickle Cell Foundation for the construction, tooling, and training of the personnel for the first-ever Sickle Cell and Blood Centre in Ghana at KATH.
Members of the KATH Board who were visibly worried about the situation expressed grave concerns about the delay of the project and said it could affect the cost of the project and further delay its completion.
The board appealed to the GNPC to honour its pledge and pay the contractor to enable them to complete the project.
When completed, the center will serve as a one-stop for the management of all sickle cell cases and blood transfusion-related services for the northern half of the country.
Latest Stories
-
Jail corrupt officials in galamsey fight – Haruna Iddrisu to Judiciary
18 minutes -
Walewale MP dismisses forest mining ban as a superficial response to galamsey
30 minutes -
Chiefs must be central to galamsey fight – National House of Chiefs President
36 minutes -
Youth joblessness a security risk as 1.3m remain idle – Opare Addo
39 minutes -
You can’t levy athletes to Fund Sports Bill – Former Sports Minister
41 minutes -
Adu-Boahene trial: Testimony of prosecution witness favouring our defence – Atta Akyea
42 minutes -
Attorney-General lauds EOCO’s Executive Director
42 minutes -
Eastern Regional FDA undertakes operation against unregistered baby diapersÂ
44 minutes -
Local Government Ministry steps up unannounced sanitation inspections ahead of Christmas
49 minutes -
Parliament passes National Health Insurance Fund Amendment Bill
54 minutes -
Government remains unshakable in retooling security agencies – Interior Minister
1 hour -
 Unemployment eases to 12.8% in Q3 2025 – GSSÂ
1 hour -
Ablakwa commissions six new buses to ease transport burden of Foreign Affairs Ministry staff
1 hour -
Mahama pledges expanded support for exporters at GEPA awards
1 hour -
Vice President reaffirms government support for trade and industrial growth
1 hour