The Parliamentary Select Committee on Roads and Transport on Wednesday, recommended to the Central Regional tender board to terminate with immediate effect the contract of Progressive and Modern Contractors Limited on the upgrading of the eight kilometre Assin Foso–Praso road for non-performance.
The contract, which was awarded in July 2004 for a sum of GH¢1,450,500 was to be completed by July 2006, but the contractor asked for an extension till June 2008, only to abandon the project.
The Committee led by its Vice Chairman, Mr Yaw Ntow-Ababio, made the recommendation, when it inspected the progress of work on some feeder roads and highways in the Assin North and Mfantseman Township, as part of their tour of the Central Region.
The committee inspected the upgrading of the 8 kilometre Assin-Foso-Praso road, Saltpond-Junction-Afrangua road and the surfacing of the 6.5 kilometre Akonfudi-Camp-Appoliningo feeder road.
Also inspected were the 6 kilometre Akropong–Odumase feeder road as well as the Saltpond town phase II roads project and the Mfantsiman girl’s school road.
Mr Ntow Ababio said it was unfortunate that the committee had to take such a decision, “but had to do so, since the government was not prepared to deal with non-performing contractors”.
The Vice Chairman was also unhappy that some contractors bid for too many contracts, which they find difficult to execute and called on the road agencies to always do proper investigations before awarding contracts to avoid shoddy works and unnecessary delay of projects.
He suggested to the Ministry of Roads Transportation to ensure that contractors were given deadlines to complete their works, and that those who fail to meet the time limit should be sanctioned.
Mr Kwabena Karkari Apau, Municipal Chief Executive of Assin North, said apart from the Kumasi-Cape Coast highway, no other road in his municipality was tarred and appealed to the committee to help address the situation.
Mr Ntow-Ababio in reply, said with the approval of a project to tar 15 kilometres of roads in each district, Assin North would be given a priority when the programme begins.Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
2026 World Cup: Messi scores twice as Argentina beat Austria
15 minutes -
2026 World Cup: Decision on Ati Zigi to be made tomorrow – Carlos Queiroz
56 minutes -
Four dead, 5 critical as 8 houses collapse after torrential rainstorm in Cape Coast
1 hour -
Corrupt citizens are termites eating foundations of development – Togbe Afede XIV
1 hour -
First Atlantic Bank petitions court to wind up Kenpong Travel & Tour Ltd over GH¢2.55m debt
1 hour -
2026 World Cup: ‘There are no easy games’ – Jordan Ayew ahead of England clash
2 hours -
The Architecture of the begging bowl: A blueprint for the extractive state
2 hours -
Interior Ministry suspends Kantanka Security Services’ licence following Adwoa Safo shooting incident
2 hours -
Police must establish whether guns used in Kwabenya shooting were registered – Security expert
3 hours -
Akatsi South Assembly suspends Acting Social Welfare Director over delayed LEAP payments
3 hours -
NSA releases postings for 18,617 nurses and midwives for 2026/27 service year
3 hours -
Photos: NDC names national headquarters after Jerry John Rawlings on 79th birthday
3 hours -
Projects are five times more likely to succeed when complexity is managed effectively- PMI research finds
3 hours -
School heads will fully comply with ban on extravagant graduation celebrations – CHASS
3 hours -
Adwoa Safo was serving court injunction when shooting occurred – Family
3 hours