Barring any technical hitches, residents of Accra East would have water supply restored on Thursday after a 10-day water interruption in some parts of Accra necessitated by expansion works to boost the quantity of water supply to the area.
The Ghana Water Company Limited (GWCL) on Tuesday August 26 shut down the pumps at its East Accra booster station to increase the capacity of the pumps to supply more water.
Mr. Samuel Kodwo Yeboah, Station Manager of the Accra booster station, announced this when the Chairman of the Public Utilities Regulatory Commission, Professor Kwabena Frimpong Boateng, and some commissioners visited the project site to assess the extent of work.
The three-prong project aims to increase the amount of water pumped at Weija by 50 million gallons, installed new pipe lines to Accra Resevoir and a panel to enhance flow of electricity.
Mr. Yebaoh said at the end of the project, communities in eastern Accra, including Adenta, Madina, Pantang, University of Ghana, GIMPA and surrounding areas would experience an enhanced water supply when work to link the pipes from the Weija Dam to the Accra Booster Station at Okponglo was completed.
The project dubbed: "East-West Interconnection Project," would make it possible to link water supply from the Weija Dam to the Accra Booster Station so that excess water from Weija could be channelled to the eastern parts which do not have constant water supply.
Water from the Kpong Dam and Weija will be connected in a way that would make Wieja supplement supplies from Kpong. As part of the project GWCL is replacing the old pumps at the booster station.
The old pumps, which currently have the capacity to pump about 130,000 gallons of water per hour, would be replaced with new ones, which have higher capacity to pump about 260,000 gallons of water per hour.
Prof. Frimpong Boateng said he was impressed with the level of work, especially the support of the Electricity Company of Ghana in providing two dedicated lines to the booster station to ensure constant water supply.
He expressed the hope that on completion of the project, water supply to the eastern part of Accra would be improved.
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Rethinking intelligence in the age of Artificial Intelligence
4 minutes -
‘Every day is about survival’ – Workers demand action beyond May Day celebrations
5 minutes -
Clear leadership demonstrated in managing recent power crisis – Dr Theo Acheampong
7 minutes -
Accountability is defective in the energy sector – Ben Boakye
9 minutes -
From detection to creation: Why education must move beyond AI plagiarism
11 minutes -
Ghanaians keep paying for inefficiencies in the power sector – Prof Bokpin
11 minutes -
Ghana’s power system not robust, outages inevitable – Ben Boakye
12 minutes -
Beyond insults: The I.D.E.M playbook for political parties in the age of the ‘social media minister’
15 minutes -
Germany backs Moroccan sovereignty in Sahara dispute
34 minutes -
Beyond Competence: How capacity shapes professional access and influence
35 minutes -
Chamber of Mines calls on BoG to release full breakdown of mining export proceeds
44 minutes -
We appeal to Ghanaians for patience as we replace more transformers – Energy Minister
60 minutes -
Power stability has improved since 2025 compared to 2024 – Jinapor
1 hour -
Akosombo substation fire should never have happened – Ben Boakye
1 hour -
Savannah region: Yazori Chief issues election boycott threat over underdevelopment concerns
1 hour