The Kumasi International Airport is set for operations in August this year, two months ahead of its scheduled completion date.
Currently, some equipment have been installed with simulation exercise completed.
The scope of work on the Airport includes the extension of existing runway pavement from 1,981 metres to 2,320 metres.

The construction of a new taxi link and apron, as well as two new apron parking stands, is among other essential facilities.
The terminal will have the capacity to handle 800,000 passengers per annum.
Presently, the terminal building is near completion with most installations done, while works on the control tower are in an advanced stage.
Ashanti Regional Minister, Simon Osei Mensah, during an inspection at the facility, expressed satisfaction at work done so far.
“Of the greatest importance to me is that they have the best scanner which can allow flight from here to move to even the United States which has the most difficult eligibility criteria in terms of aviation; they say the scanner we have qualifies for the requirement of the US Airlines,” he said.

He added: “If you look at the departure and arrival hall, it’s almost completed. All the facilities have been installed but you will need the fire service area, the control tower and others, which once completed, will have a simulation exercise.”
Once works on the project are completed, the existing terminal which has outlived its usefulness is expected to be demolished.

As part of government’s vision to expand economic activities in the city, efforts are being made to improve infrastructure.
Already, a 100km town road project within the Greater Kumasi enclave has been completed by Contracta Construction.

Mr. Osei Mensah says the government is committed to developing majority of roads in Kumasi by the end of its tenure.
“People say they don’t see the roads, it’s because some of the roads are localised. If you are not living here at Kentinkrono, how do you know this road is constructed?

"As you can witness, excluding other contracts within the Greater Kumasi enclave, we are expecting 400km of road constructed. By the time it is done we would have covered many areas in Kumasi,” he emphasised.
Latest Stories
-
NSA to close registration portal for 2025/2026 National Service year
2 minutes -
BoG Governor targets single-digit interest rates to boost businesses
21 minutes -
BAWA-ROCK Ltd honoured for sustainable gold trading at Africa Development Conference
30 minutes -
Fire guts Unique Floral shop at Tse Addo
1 hour -
GPL 2025/26: Kotey strike hands Gold Stars crucial away win at Hohoe
1 hour -
Dormaahene urges Mahama to pursue accountability over National Cathedral project
1 hour -
GPL 2025/26: Mamah strike powers Samartex past Heart of Lions
1 hour -
Mahama directs release of GH¢1bn to contractors owed since 2017
1 hour -
GPL 2025/26: Aduana hold Hearts in Dormaa
1 hour -
Sekyi-Brown Reginald: Transforming infrastructure into preventive healthcare
1 hour -
Two arrested for unlawful possession of firearm, ammunition
2 hours -
GPL 2025/26: Karela United edge Vision FC in Tamale
2 hours -
Return home to support 24-hour economy agenda – Ambassador Smith urges students abroad
3 hours -
Minute’s silence held to remember Bondi Beach attack victims
3 hours -
Lands Minister commissions 3rd batch of 636 Blue Water Guards; pledges sustained fight against galamsey
3 hours