The Testing and Commissioning phase of the Ghana Gas-West African Pipeline Company Limited (WAPCo) Interconnection Project is almost completed.
This follows successful completion of engineering and construction work on gas pipelines from Sanzule through to the Takoradi Regulatory and Metering System (TRMS) of the Volta River Authority at Aboadze.
Head of Communication at Ghana National Gas Company Limited, Ernest Owusu Bempah, during an inspection visit of the project site on Monday said, the exercise involves some protocol that needed to be adhered to so as to ensure the safety and efficiency of the pipeline system.
“They need to check the pressure, understand how the flow is going to be like, detect any possible leakages, technically to make sure that everything is fine before they start pushing the gas,” he stated.
Mr Owusu Bempah disclosed that the company is currently producing about 37million metric cubic feet of gas to the Volta River Authority for the testing and commissioning phase of the pipelines.
The success of testing would enable them to roll out fully the production and supply of gas through the TRMS to the Eastern enclave to power up thermal plants.
“At the moment we doing about 37 million cubic feet on the pressure within the testing and commissioning, from there it can take about 60 million cubic feet of gas; which is very significant as it can do about 300 megawatts of electricity” he added.
He is highly optimistic that the recurring gas shortage, which in the past hit power-producing plants in the country will be extinguished.
“…there’s not going to be any problem when WAPCo tells us there’s not enough gas available. There will be more gas flowing…we will be doing about 30 to 60 million cubic feet of gas to help us generate electricity,” he elaborated.
The Officer-in-charge of Pipeline and Station at the TRMS, Emmanuel Ackon clarified that the testing and commissioning phase of the project begun on Thursday, May 16.
According to Mr. Ackon said should things go according to plan, the exercise he described as “far excellent”, would be completed in the next couple of days.
“They need to check the pressure, understand how the flow is going to be like, detect any possible leakages, technically to make sure that everything is fine before they start pushing the gas,” he stated.
Mr Owusu Bempah disclosed that the company is currently producing about 37million metric cubic feet of gas to the Volta River Authority for the testing and commissioning phase of the pipelines.
The success of testing would enable them to roll out fully the production and supply of gas through the TRMS to the Eastern enclave to power up thermal plants.
“At the moment we doing about 37 million cubic feet on the pressure within the testing and commissioning, from there it can take about 60 million cubic feet of gas; which is very significant as it can do about 300 megawatts of electricity” he added.
He is highly optimistic that the recurring gas shortage, which in the past hit power-producing plants in the country will be extinguished.
“…there’s not going to be any problem when WAPCo tells us there’s not enough gas available. There will be more gas flowing…we will be doing about 30 to 60 million cubic feet of gas to help us generate electricity,” he elaborated.
The Officer-in-charge of Pipeline and Station at the TRMS, Emmanuel Ackon clarified that the testing and commissioning phase of the project begun on Thursday, May 16.
According to Mr. Ackon said should things go according to plan, the exercise he described as “far excellent”, would be completed in the next couple of days.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
From Deputy to Defense Boss: Gilbert Adjei returns to lead ministry where he once served number two
12 minutes -
Government targets 10% renewable energy mix by 2030, tasks BPA to lead expansion
12 minutes -
Beverly Afaglo’s funeral to be held at State House on August 8
22 minutes -
IMF warns Ghana of elevated financing needs due to large rollover of T-bills in 2027-28
26 minutes -
Illegal mining is threatening Ghana’s food security, not just environment — Ghanaian Farmer CEO
39 minutes -
Delayed construction projects creating air pollution and health risks for people across the country
39 minutes -
Bui Power Authority records US$66.2m profit as solar expansion boosts 2025 performance
44 minutes -
Who is Kenneth Gilbert Adjei? The former Deputy Defence Minister returning to lead Ghana’s Defence Ministry
44 minutes -
From stabilisation to sustainability: building a resilient and inclusive financial sector for Ghana — the role of ICDFA
1 hour -
IMF upgrades Ghana to moderate risk of debt distress
1 hour -
Saudi Arabia, Turkey and Pakistan sign defence pact
1 hour -
Vice President bids farewell to outgoing Brazilian Ambassador, reaffirms Ghana-Brazil partnership
2 hours -
Losing the next generation? Ghana cannot afford to ignore youth substance abuse
2 hours -
Nalerigu SHS ends Bunkpurugu’s reign to return to NSMQ after three years
2 hours -
Standard Chartered declares GH¢673m dividend at 56th Annual General Meeting
2 hours