The Auditor-General has uncovered a staggering ¢44 million worth of abandoned projects and completed projects not put to use across the country.
In its latest report on management and utilisation of the District Assemblies Common Fund (DACF), the Auditor-General found that many assemblies spent millions on projects only to abandon them before they are completed.
In all, the Auditor-General uncovered contract irregularities worth ¢45 million in 107 assemblies.
The Auditor-General also found cases where payments were made although contractors failed to do the job.
The Auditor-General has recommended recovering payments for unexpected contracts and justified contingencies from the Chief Executives, Coordinating Directors, Finance workers and engineers.
Latest Stories
-
NAIMOS seizes excavators and shuts down illegal Riverbank mining in Eastern Region
1 hour -
NAIMOS dismantles illegal foreign mining network along the Bia River
2 hours -
Zelensky signals progress in talks with US on peace plan
3 hours -
Policemen assaulted in Jirapa; AK-47 rifles stolen
4 hours -
Bibiani tragedy: Toddler killed by moving Toyota Pickup
5 hours -
Don’t scrap OSP – Anti-corruption CSO demands review
6 hours -
GIS, EU vow closer security cooperation to boost northern border control
7 hours -
IGP leads major show of force with new armoured fleet
8 hours -
Two female prison officers killed in ghastly crash
8 hours -
Abolish or Reform? Abu Jinapor counsels sober reflection on debate over future of Special Prosecutor’s Office
10 hours -
2026 World Cup: Can Ghana navigate England, Croatia, and Panama in Group L?
10 hours -
NAIMOS task force arrests 9 Chinese illegal miners, destroys equipment at Dadieso
11 hours -
NAIMOS advances into Atiwa Forest, uncovers child labour, river diversion and heavy machinery
11 hours -
NAIMOS Task Force storms Fanteakwa South, dismantles galamsey operations
11 hours -
The Kissi Agyebeng Removal Bid: A Look at the Numbers
12 hours