A former Power Minister under the John Mahama administration, Dr. Kwabena Donkor, has called on parliament to probe the former Energy Minister, Boakye Agyarko and other officials of the New Patriotic Party (NPP) administration, who took the decision to terminate the power purchase agreement with the Ghana Power Generating Company (GPGC), leading to a judgement debt of $140 million.
The Ghana High Commission building in the UK, which provides visa and other services, the commissioner's residence, the Ghana International Bank building, and other properties are at risk of being auctioned to defray a $140 million judgment debt awarded to Singaporean firm, Trafigura.
Trafigura, the majority owner of the power company GPGC, secured the award in January 2021 after an arbitral tribunal in London found that Ghana had unlawfully terminated a contract for the installation and operation of two power plants.
The government says the Finance Ministry has taken steps to liquidate the debt, but Ghana’s High Commissioner to the United Kingdom, Papa Owusu Ankomah, believes the financial constraints of the government are to blame for the default in the payment as agreed with the judgement creditor.
Upon the advice of the Attorney General in 2017, the government terminated the deal on grounds that due to its attendant high tariffs, if implemented, it would have cost the state $115,480,000.
It also cited illegality for want of capacity of [GPGC] to enter into a PPA, failure to obtain siting and construction permits, installation of used plant contrary to policy, and failure on the part of GPGC to fulfil some conditions among others.
But the former Power Minister said the reasons given for the termination are untenable. Speaking on PM Express on Tuesday, October 24, he argued that the GPGC deal was the cheapest and shortest among all PPAs signed at the time.
He insisted the quantum of judgement debt now to be paid by the government was avoidable.
“It was very avoidable as I have always said. Let me quickly say this. This was the cheapest of all the emergency power plants in terms of cost. It was also the shortest because it was for four years. There was no requirement for the government of Ghana to put down a guarantee, and then again the total capacity charge made of capital recovery, fixed ONM, and non-fuel variable ONM came to 4 cents per kilowatt hour. It was the cheapest at the time of all the emergency power plants we brought in, and so it couldn’t have been on the basis of cost.”
Dr Kwabena Donkor also explained that the government’s claim that GPGC failed to obtain siting and construction permits, was neither here nor there since that responsibility was partly on the state as stated in the contract.
“Every contract, at least power contracts, contain conditions for termination. My worry at the time and I raised the alarm, was that the letter signed by the then Energy Minister Boakye Agyarko, stated that Trafigura or the Ghana Power Generating Company [GPGC] which was the subsidiary we had signed the contract with, had not obtained all the necessary Energy Commission permits.
“In the Power Purchase Agreement, one of the obligations of the government of Ghana was to assist the contractor obtain all relevant government of Ghana permits. And so if we turn around to use that as the basis for termination it creates a problem for all of us.”
While admitting that the government reserved the right to terminate any agreement it wanted, he said the state failed to follow due process in terminating the contract.
Let me concede that the government of the day can decide to terminate any contract, but there are consequences for termination. And in all agreements, there are conditions and processes for termination, and so if you do not follow the processes and conditions, particularly if the termination is not justified as ruled by the arbitration panel, then we are in trouble, and this is exactly what has happened” he insisted.
If we had negotiated the termination, we could have even taken ownership of the equipment. Unfortunately, even after the court had ruled, we went to sleep. Trafigura is still doing business in Ghana, and therefore we had some leverage at least in negotiating a payment plan, but all the way from 2021 we went to sleep.
The Pru East MP also rubbished the government’s argument that the plants were used or obsolete, insisting that information was not hidden. He also argued that the GPGC plant was not the only used plant the country had secured.
“Yes, it is used equipment and it was known at that time. It was not the only used equipment that was brought in. The AKSA plant was also used, it wasn’t new. And so, for AKSA we signed a 5-year agreement, and the government has found it necessary to extend this agreement for another 10 years, so the question of the equipment being used is neither here nor there.”
The legislator wants those responsible for the termination to answer critical questions.
“I believe the Ghanaian state should ask the people who took the decision to terminate to tell us why they terminated. I believe that is the route to use if we have to improve our governance. Those who were responsible would have to tell us why they took that decision because commercially, and legally it doesn’t make sense.”
Even from an energy perspective, you don’t terminate the cheapest emergency plant you have. And then if you say it was an old plant, we knew it. AKSA was also an old plant, we signed for five years as an emergency plant, but this government has gone ahead to extend it for a further ten years. And so if you add all these, we find it extremely difficult to justify. Maybe Hon. Boakye Agyarko who signed the letter may be able to tell us what some of us don’t know”he added.
I believe parliament is the best institution to do that because the decision to terminate was taken by the executive arm, and so you cannot ask the executive arm to investigate it. Ghanaians must know why, we have the right to know.”
Latest Stories
-
Don’t play ‘chaskele’ with pension funds; stop sale of hotels to Bryan Acheampong – TUC warns
12 mins -
Faulty undersea cables fixed; Telcos call for better cable infrastructure protection
16 mins -
Customs confiscates Burkina Faso-bound fish truck diverted to warehouse in Kumasi
23 mins -
Minority demands forensic audit of World Bank, GARID operations
32 mins -
2 killed in horrific accident on Adukrom-Somanya highway in Eastern Region
47 mins -
Asantehene @25: The man who carried the revered Golden Stool
52 mins -
Limited registration: 2 Togolese arrested in Buem for attempting to register
58 mins -
2024 polls: Be vigilant and ensure the right things are done – Mahama to clergy
1 hour -
SSNIT hasn’t responded to the fundamental issue; how was Rock City selected? – Ablakwa asks
1 hour -
PETROSOL appoints former CEO of VALCO as its Board Chairman
1 hour -
‘I am ready to get it running next season’ – Kudus after debut Premier League campaign
2 hours -
Oliver Barker-Vormawor fumes as his treason trial is adjourned again
2 hours -
Okomfour Kwadee’s condition is ‘family matter’ – Quick Action
2 hours -
Fidelity Bank vs Bright Simons: High Court adjourns case to July 4
2 hours -
Western lifestyle imitation contributes to rising diabetes among Ghanaians – Dr Beatrice Baaye
2 hours