The Bui Power Authority says the dam will return to producing power at capacity by July, when the flow of water into its reservoir is expected to improve significantly.
The 400 -megawatt hydro-power installation has currently shut down two of its three turbines and stopped generating active power.
Instead, the dam is producing reactive power, a remedy for low system voltage, by means of air and a single turbine according to Wombila Salifu, External and Community Relations Manager of Bui Power Authority.
“We have not shut down,” he said in an interview, adding: “we are not generating active power with water now due to the low water level. We are running one unit now and producing 50 vars of reactive power”.
He further stated: “According to the weather pattern over the years, we expect to return to full generation by July. In July, August and September, we get a lot of inflow into the reservoir. At the moment we are getting some inflow, but it's small. If we get a level of water that is adequate, we will produce”.
The reactive power being produced will boost voltage in the northern part of the country to the transmission network requirement of 161 kilowatts, he said.
Bui has a maximum water level of 183 metres above sea level (masl) and a minimum operating level of 168 masl. But in a statement issued last week the Authority said it has been over-drafting - drawing more water from the reservoir for power generation -- in response to inadequate electricity generation from the Volta River Authority, which provides 75 percent of the country's power needs.
The Authority noted with great concern that “as a result of the Bui reservoir reaching the minimum operating level, the rate of power generation has been reduced in order to protect the turbines from potential damage.
This is because it is imprudent to operate the generating plant below the minimum operating level of the reservoir, as this unduly exposes the turbines to higher risks of damage”.
Bui's partial shutdown has compounded the generational shortage, causing the Electricity Company of Ghana to cut supply to households.
The power cuts will however be minimised during the ongoing World Cup, the Public Utilities Regulatory Commission (PURC) announced this week.
The PURC said it has agreed with the utility service providers that “all available generating units should be on- stream during the tournament, and maintenance personnel will be posted to man critical substations and installations during the match periods to ensure expeditious restoration of electricity in the unlikely event of an unplanned outage or emergency”. It said the country will buy 50 megawatts of extra power from Cote d'Ivoire, and VALCO's consumption will be reduced on days when the Black Stars are playing.
But this contingency plan does not mean a complete end to power cuts, it stressed.
“It should be noted that these plans are put in place for consumers to watch uninterrupted football matches during the World Cup tournament, ;but within these arrangements the load- shedding schedule, though varied, still exists.”
Latest Stories
-
Hurricane Polo makes landfall on Mexico’s Pacific coast
21 seconds -
US ban on Canadian alcohol and dairy comes into effect as trade war drags on
2 minutes -
GES orders SHS heads to refund unauthorised fees collected from parents
10 minutes -
AFCON 2027Q: ‘We don’t need to cry over spilled milk’ – Damba on Ghana injury concerns
14 minutes -
NDC communicator blames documentation, payroll validation for teachers’ promotion arrears delay
15 minutes -
2026 JoyNews Impact Maker Award winner brings clean water to Yoko Tsume after years of cattle dugout dependence
22 minutes -
Sarkodie commends Mahama for rejecting US health compact
22 minutes -
‘The worst hate speech comes from NDC; enough of lip service, optics politics’ – Afenyo-Markin to Mahama
22 minutes -
Tree Crops Development Authority tightens regulation of tree crop trade, targets $10bn sector
23 minutes -
Ghana’s fiscal deficit to widen to 3.9% a year through 2029 – S&P
23 minutes -
‘It’s not a matter of evidence; it was a metaphor’ – Afenyo-Markin defends ‘drug lab’ comment
36 minutes -
Borrowing costs cut by more than half – Finance Minister
39 minutes -
KNUST students urged to look beyond Ghana for AI and robotics opportunities
42 minutes -
Odeibea Foundation extends energy equity initiative with solar streetlights in Akpato and Worwonyo
43 minutes -
Customs increases surveillance at ports, warns importers against concealing restricted items
45 minutes