Power has been restored to most parts of the Greater Accra, Central and Eastern regions where there were power outages resulting from an outbreak of fire which destroyed a transformer at the Ghana Grid Company Limited (GRIDCo) bulk supply station at Dzorwulu in Accra on Saturday.
However, GRIDCo has indicated that it would be able to replace the damaged transformer with a new one by the end of February, this year.
The fire completely damaged the 66 Mega Volt Ampere (MVA), one of five transformers which supply power to the affected areas.
The incident happened at about 5 p.m. last Saturday during a downpour.
According to the Head of Public Relations of GRIDCo, Mr Albert Quainoo, lightning might have struck the transformer, causing it to catch fire.
"Indeed our engineers were there within minutes, and the first thing to do was to isolate four other transformers from the one that caught fire," he said.
He told the Daily Graphic that the company had spare transformers in Tema, and that one of such transformers would be brought in to replace the burnt one.
Mr Quainoo'said the company engineers would work feverishly to replace the burnt transformer.
He said the damage of the transformer would not affect the supply of power, since there was a backup support from other substations.
For instance, he said, Adjiriganno had a 132-MVA transformer of which 31-MVA was being used, and that the other load would be transfered to customers.
Again at Mallam in Accra, he said, there was an upgraded substation which could also supply power to customers.
He added that there was enough capacity in the system to supply to customers.
In the first two weeks of this year, 265 fire outbreaks have been recorded in different parts of the country.
Shortly after the fire incident at Dzorwulu, personnel from the ECG and the GRIDCo had to move in to separate the four other transformers from the transformer that caught fire.
The police were also called in to ensure law and order following the movement of people to the area.
Personnel from the Ghana National Fire Service (GNFS) battled the fire for over an hour before putting it out.
A visit to the substation Sunday revealed a badly damaged transformer which was said to have two pairs of lightning arrestors.
Each pair contains three arrestors. One pair each is for the low and high side of the transformers.
Investigations are ongoing as to how the lightning was able to strike the transformers even though it had arrestors.
Residents said they were greatly affected by the outage that followed as a result of the damage to the transformer, since they did not expect it.
The ECG is currently undertaking an emergency load-shedding exercise as a result of relative instability in electricity supply.
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Seamless Technologies CEO Calls for Strategic AI adoption to transform Ghana’s financial services sector
2 minutes -
Cargill, ICI equip 111 youth with vocational skills to tackle child labour
4 minutes -
Council of State member donates $5,000 to NDC UK and Ireland Aldershot branch for water project
9 minutes -
Education Ministry renews return-to-class appeal despite teachers’ refusal to end strike
14 minutes -
Remains of dozens of suspected kidnap victims found in Nigerian forests
14 minutes -
Four bodies found after avalanche hits Himalayan climbing group
20 minutes -
Adipa residents give government seven days to halt Agbogbloshie waste transfer
30 minutes -
Desks rotting in abandoned Kintampo South E-Block: A decade of neglect and a waste of state resources
32 minutes -
West Africa cannot simply import security models without accounting for local realities – WAMS
33 minutes -
Bono East Minister directs MCE to stop hotel project near Konkrompe SHS
55 minutes -
AGN Chair urges action-driven tracking and reporting on inclusive climate adaptation in Ghana’s agriculture
58 minutes -
Man City rule breaches not my concern – Mancini
58 minutes -
NSA releases PIN Codes for 2026/2027 national service private candidates and foreign-trained graduates
1 hour -
GMet forecasts thunderstorms, rain across parts of Ghana this evening
1 hour -
APRA wins Africa PR Legacy Award
1 hour