Audio By Carbonatix
Ghana Grid Company (GRIDCo) 330kV Kumasi – Bolgatanga transmission line project has been formally commissioned by President Nana Addo Dankwa Akufo-Addo.
The project was funded by a French Development Agency (AFD) facility of $174 million and a European Union grant of 5 million dedicated to the Project Management and Supervision.
The project works commenced in March 2016 and was completed in October 2021.

The project construction was undertaken by Elecnor S.A. for the Kintampo Substation, Eiffage Energies/ABB AG J.V. undertook the Tamale Substation works, while the Bolgatanga Substation was done by Sinohydro Corporation Limited and KEC International involved the construction of approximately 551 km of 330 kV Transmission Line from Kumasi in the Ashanti Region to Bolgatanga in the Upper East Region.
The Project was part of WAPP regional interconnection project between Ghana and Burkina Faso. It was jointly implemented in Ghana and Burkina Faso by GRIDCo and SONABEL enabling the export of 150MW of power to Burkina Faso.

Chief Executive of GRIDCo, Ing. Ebenezer Essienyi commented, “GRIDCo is proud to have delivered this complex energy sector project with the support of strategic partners which has a direct impact on power supply for Ghanaians, businesses and foreign customers.
"This transmission line project reinforces and stabilises GRIDCo’s transmission network. It also expands access for Ghana’s middle to northern belt, as well as consolidating Ghana’s export of up to 150 MW beyond its northern border to Burkina Faso and the Sahel region. I commend all who were involved for their contribution to make this project a reality”.
The project allows the reduction of transmission losses, increased transmission capacity and improved security of electricity supply to Burkina Faso and other neighboring countries.

France and Europe congratulate GRIDCo for completing this critical infrastructure. The project is already starting to have huge benefits for the Ghanaian people by improving the reliability and efficiency of power transport and distribution up to Northern Ghana.
As the Chargé d’Affaires A.I. of the French Embassy to Ghana, Raphaël Malara adds, “I do consider that such a project - by enhancing regional integration and facilitating the provision of basic services - is a contribution to stability and peace in the region. This project is also a reflection of the importance of the Energy Sector for the partnership between France and Ghana.”
This Project has increased transmission capacity to meet growing demand in Ashanti, Northern Ghana and Burkina Faso.
GRIDCo continues to improve its transmission assets, quality power supply in Ghana and beyond to effectively carry out its mandate of being the model Grid Company in Africa.
These efforts will impact positively on the Socio-economic development of Ghana and Africa as a whole
Latest Stories
-
SONABEL considers opening Bagré Dam spillway on Friday amid rising water levels
2 minutes -
Ghana Maritime Authority, Humanity First commission 4 boreholes in Wa to end water scarcity and keep children in class
13 minutes -
In Photos: Day Two of ‘SYPALA 2026’ focuses on governance, economic freedom and youth leadership
29 minutes -
Wontumi withdraws from NPP chairmanship race, urges support for Bawumia
48 minutes -
UCC-IEPA, CEGRAD launches free digital skills programme to empower 1,000 women in education
54 minutes -
NPP dismisses extortion allegation against Afenyo-Markin, says focus remains on GoldBod losses
1 hour -
Guinness Ghana DJ Awards 2026 set for December 4 as ‘All Out’ era begins
1 hour -
GhIE inducts 183 engineers, calls for stronger action on galamsey and infrastructure
1 hour -
Thousands of children receive free specialist care at Asafo-Boakye Specialist hospital fair
1 hour -
I’m yet to receive official confirmation of Wontumi’s Chairmanship withdrawal – Opare Ansah
1 hour -
Independent voices must be part of gold programme probe – Dr Rasheed Draman
2 hours -
ACEPA backs full probe of Domestic Gold Purchase Programme from inception
2 hours -
KNUST Statutes update sparks fresh debate as staff challenge official narrative
2 hours -
NUTE must strengthen 49 colleges, not become another public university – Eduwatch
2 hours -
Awal Mohammed files for Nasara Organiser, vows to rebuild NPP Nasara structures ahead of 2028
2 hours