The Africa Centre for Energy Policy (ACEP) has stressed Ghana's power supply situation is in a "fragile state" despite assurances from the Volta River Authority (VRA).
Head of policy at ACEP Dr Ishmael Ackah told Joy News on Monday that all that stands between a return to the era of the erratic power supply is 98 MW.
Despite an installed power capacity of 3,800, Ghana's power generation mix is producing 1842MW with a total demand is about 1740MW.
It means if generation capacity falls below 98MW, ECG would have to "on a place and off a place as we used to have", Dr. Ackah said.


Breaking down the challenges, Ghana's gas supplier FPSO is set to go for repairs next month resulting in a gas cut to Ameri which generate 220MW.
Reserve plants Asogli and Kpong in the Tema enclave rely on gas from Nigeria. But with a debt around $185 million as at November 2016, getting more gas from Nigeria means Ghana would have to lower its debt profile with the West African giant.
In effect, money will be key in keeping at bay an erratic power supply regime which lasted 2012 to 2015.
Without gas for Ameri, Asogli or Kpong thermal plants, consumers also rely on TAPCO 1&2 thermal plants in Takoradi in the Western region which uses LCO.
Anxiety about reliable power has re-surfaced after the VRA revealed the Takoradi Thermal Plant Stations (TAPCO 1&2) are off the grid for repairs and maintenance. This translates into a loss of 330MW of power.
This is because the contractor for the VRA’s long-term service agreement refused to carry out a major inspection. It was to pressurise government to pay a $2 million debt owed it.
But Head of Corporate Communications at the VRA, Gertrude Koomson has explained, the power generator is in the position to manage the situation.
"We have no doubt as we speak today...we have put in place adequate preparations. We enough LCO to even last us two months," she stressed.
Latest Stories
-
Crowds, deals and home solutions as Republic Bank-JoyNews Habitat Fair enters final day
46 minutes -
Fire Service finds only five functional hydrants in Ministries enclave
1 hour -
Government to sign 1,200MW gas power deal before end of 2026 – Mahama
1 hour -
West Mamprusi launches community-led WASH and livelihoods project across 100 communities
1 hour -
Iran says it will wait for official US response after Trump rejects Strait of Hormuz proposal
1 hour -
90 Oti communities to benefit from government electrification project
1 hour -
Floods leave 246 without shelter as 93 houses collapse in North East Gonja
2 hours -
Labour Minister wants SOEs to help shape new public pay system
6 hours -
IPEC will ensure Equity and Sustainability in SOEs Compensation
7 hours -
White House bars CNN from travelling with Trump on Air Force One
7 hours -
Fennis wins second consecutive ITF J60 title in Accra
8 hours -
Spain beat England in thriller after Kane penalty miss
8 hours -
GPL 2026/27: Zaidan’s late goal ends Hearts of Oak unbeaten start
8 hours -
CEOs demand clarity on pay harmonisation, board autonomy as FWSC engages SOEs bosses over IPEC transition
8 hours -
2026 Women’s Super Cup: FC Savannah, Epiphany Warriors maintain top spots ahead of final group games
8 hours