Michelleti Limited, the company constructing the new-look Ohene Djan Stadium, has admitted that portions of the tartan athletics tracks at the $2.7 million refurbished El Wak stadium were not properly done.
It has accordingly given an undertaking to rectify the defects before the National Athletics Championships are held later in the month.
The construction firm, however, maintains that it took the best professional processes possible to ensure the project was sub-contracted to a competent firm which certified that the project was done over five weeks in compliance with international standards and run a number of tests on it before handing it over.
Reacting to an expose in last Friday's edition of the Graphic Sports, which laid bare the defects on the athletics tracks and criticisms by top national athletes and officials, Mr Stuart Ward, Project Manager of Micheletti Limited, acknowledged that portions of the tracks which had developed cracks and were peeling off were not properly done by the Italian firm, Artigian Service Group.
But he insists the firm has experience in constructing athletics tracks in Africa. The company's website www.artigianservice.com lists at least nine athletics tracks and several synthetic football fields as projects it had undertaken in Algeria between 2002 to date.
Also, following safety concerns raised by athletes over the unusual existence of concrete surface at the end of the long jump pit, Micheletti has ordered Artigian to ensure the concrete surface is replaced with tartan surface in conformity with international standards.
"I admit that the width of the synthetic surface at the area where the javelin takes place is not thick enough, so I have asked the sub-contractor from Italy to come back and fix it," Mr Ward told the Graphic Sports last Monday. "That's the only problem area but the rest of the tracks are ok and have the right thickness," he stressed.
Micheletti undertook landscaping and construction of the sub-structure with asphalt, while Artigian Services laid the tracks with synthetic materials that Mr Ward insists were certified by track and field's world governing body, IAAF.
"The materials used were certified, and based on the test report given by the company, there's nothing to show the facility is not compliant," Mr Ward said.
Last week, athletics officials including the chairman of the Ghana Athletics Association, Mr Sandy Osei-Agyeman, questioned the competence of the contractors in the face of the problems encountered on the EI-Wak tracks. However, for the Micheletti official, the criticisms about the company's track record are misplaced.
Despite defending Micheletti's due diligence and procedure taken in awarding the contract, Mr Ward promised to rectify other defects that are identified at EI-Wak.
"We vetted companies that sent in proposals and went through the best practices possible in the procurement before selecting a company with the right credentials, but if the athletes have specific problems, we have to deal with them.
"We have already written to the company to come back and rectify the faults but they have not responded quickly enough because their personnel are currently working on the tracks at the Baba Yara Stadium," he said.
Source: Graphic Sports
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Health Ministry moves to integrate traditional medicine into mainstream healthcare
15 minutes -
550 pupils in Kintampo South get educational lifeline as ‘Seeds of Hope’ reaches farming communities
35 minutes -
Opoku Mensah urges Christian Council, House of Chiefs to speak up on democratic freedoms
52 minutes -
Teacher unions’ strike: Minority demands immediate payment of teacher arrears, 20% deprived area allowance
1 hour -
The Accra-Kumasi Expressway: Building it right
1 hour -
Beyond gold exports: Building value and economic resilience from Ghana’s gold
1 hour -
2027 AFCONQ: Ghana under pressure as Gambia beat Somalia 2-1
1 hour -
Eastern NPP Women’s Organiser calls on AG, Police to secure bail for Salomey Baffoe
2 hours -
Poverty, illiteracy driving acceptance of vote-buying among women – Damongo Queen Mother
2 hours -
Photos: Democracy Is Not For Sale forum in Savannah region
2 hours -
GNFS launches 2026/27 National Anti-Bushfire campaign in Atebubu, records 62.8% reduction in bushfire cases
3 hours -
I’ll vote for a female president; women are less likely to steal from the state – Okyeame Kwame
3 hours -
More public education needed to stop vote-buying – Savannah Region MP
3 hours -
Absa Bank commissions new head office, commits to strengthening operations in Ghana
3 hours -
Republic Bank-JoyNews Habitat Fair clinic: Day 1 ends on positive note as patrons explore housing solutions at Junction Mall
3 hours