Audio By Carbonatix
Construction works on the Tema-Aflao highway resumed on April 7, 2025, after a 15-month suspension, but fresh concerns are emerging over delayed funding that could threaten the project’s smooth execution.
Contractor BHM International, responsible for the 17-kilometre stretch between the Kpone-Barrier and the Central University campus at Miotso, says the $105 million loan facility earmarked for the project has still not been reinstated.
Client Relations Manager at BHM International, Wisdom Adonoo, speaking to JoyNews after a visit to check progress of work warns that the longer the delay persists, the greater the risk of slowing down or even stalling progress which is scheduled for completion in 18 months.

“We are still waiting for the loan to be reinstated. In the meantime, we are working in good faith based on the minister’s assurance in April, and we are committed to delivering this project on time. But the longer the funds delay, the more difficult it becomes to execute the work as required by contract.”

A visit to the site shows significant improvements compared to five months ago. On the Tema-to-Aflao side, contractors have expanded the road by adding more lanes.

Most sections have already been filled and opened to traffic during peak hours, easing congestion that road users previously complained about.
On the Aflao-to-Accra side, excavation is still ongoing across several stretches, with heavy trucks and machinery actively at work.

BHM says the next phases include stabilisation, stone base pavement, asphalt, and pedestrian walkways, along with the completion of four planned flyovers, three of which already have structures erected.

Beyond funding, compensation for affected residents and traders remains a challenge. According to the Public Relations Officer Pastor Samson Allotey, out of 1,131 people identified for compensation, 842 have so far been paid, representing about 74.5%. Roughly half of those compensated have relocated to allow for construction, but the remaining yet to be compensated threatens work on section of the road.
“We urge government to expedite compensation for the remaining affected persons. Until payments are made and relocations completed, clearance for construction in some areas will remain an issue,” he said.
Latest Stories
-
GPL 2025/26: Dreams FC stage stunning comeback to hammer Eleven Wonders
1 hour -
Livestream: The Probe examines Kumasi’s looming water crisis
1 hour -
MTN Ghana gears up to lead Africa’s AI revolution
1 hour -
Philanthropist Alhaji FuZak donates Da’wah bus to Ambariya Sunni community
1 hour -
GUTA calls for suspension of Publican AI system over trade disruptions
1 hour -
TTAG raises alarm over proposed recruitment of 7,000 teachers, demands national posting roadmap
2 hours -
Civilians feared killed after reports of air strike on Nigerian market
2 hours -
Bishop Simon Kofi Appiah installed as new Jasikan Diocese Bishop
2 hours -
Trump’s Strait of Hormuz blockade threat raises risks and leaves predicaments unchanged
2 hours -
US Court backs extradition of former MASLOC CEO Sedina Tamakloe-Attionu to Ghana
3 hours -
Seven arrested as NAIMOS dismantles illegal mining camp, seizes firearms at Boin River
3 hours -
Fire erupts at Madina Ritz Junction, destroys multiple wooden structures and containers
3 hours -
Daniel-Kofi Kyereh returns from long-term injury, registers assist for Freiburg U23
3 hours -
Knifeman calling himself ‘Lucifer’ slashes three at NYC’s Grand Central
3 hours -
Brands are built from within to without
3 hours