Audio By Carbonatix
Construction works on the Tema-Aflao highway resumed on April 7, 2025, after a 15-month suspension, but fresh concerns are emerging over delayed funding that could threaten the project’s smooth execution.
Contractor BHM International, responsible for the 17-kilometre stretch between the Kpone-Barrier and the Central University campus at Miotso, says the $105 million loan facility earmarked for the project has still not been reinstated.
Client Relations Manager at BHM International, Wisdom Adonoo, speaking to JoyNews after a visit to check progress of work warns that the longer the delay persists, the greater the risk of slowing down or even stalling progress which is scheduled for completion in 18 months.

“We are still waiting for the loan to be reinstated. In the meantime, we are working in good faith based on the minister’s assurance in April, and we are committed to delivering this project on time. But the longer the funds delay, the more difficult it becomes to execute the work as required by contract.”

A visit to the site shows significant improvements compared to five months ago. On the Tema-to-Aflao side, contractors have expanded the road by adding more lanes.

Most sections have already been filled and opened to traffic during peak hours, easing congestion that road users previously complained about.
On the Aflao-to-Accra side, excavation is still ongoing across several stretches, with heavy trucks and machinery actively at work.

BHM says the next phases include stabilisation, stone base pavement, asphalt, and pedestrian walkways, along with the completion of four planned flyovers, three of which already have structures erected.

Beyond funding, compensation for affected residents and traders remains a challenge. According to the Public Relations Officer Pastor Samson Allotey, out of 1,131 people identified for compensation, 842 have so far been paid, representing about 74.5%. Roughly half of those compensated have relocated to allow for construction, but the remaining yet to be compensated threatens work on section of the road.
“We urge government to expedite compensation for the remaining affected persons. Until payments are made and relocations completed, clearance for construction in some areas will remain an issue,” he said.
Latest Stories
-
GPL 2025/26: Asante Kotoko draw with GoldStars to extend winless run
2 hours -
Fire guts temporary wooden structures at Afful Nkwanta in the Ashanti Region
3 hours -
Haruna Iddrisu didn’t approve gender identity content – Education Ministry
3 hours -
‘We are not for sale’: Thousands rally in Greenland and Denmark against Trump’s annexation threat
3 hours -
Deputy Education Minister directs GES to act on video of SHS students displaying charms
3 hours -
From camouflage to tracksuits – Guinea’s junta leader becomes civilian president
4 hours -
Iran supreme leader admits thousands killed during recent protests
4 hours -
Judiciary to roll out court decongestion measures, galamsey courts – Chief Justice
5 hours -
Ugandan leader to extend 40-year rule after being declared winner of contested poll
5 hours -
Residents demand action on abandoned Salaga–Kumdi–Kpandai road
6 hours -
Ghana, Japan explore ways to deepen long-standing bilateral ties
6 hours -
Ghana Navy foils illegal fuel bunkering operation along Volta coastline
6 hours -
Gov’t assures minimal power disruption during WAPCo gas pipeline maintenance
6 hours -
Burna Boy and Sporty Group unveil new single “For Everybody” celebrating Africa’s sports heritage and cultural excellence
7 hours -
Achieve By Petra partners Richie Mensah to drive financial independence
7 hours
