Audio By Carbonatix
Construction works on the Tema-Aflao highway resumed on April 7, 2025, after a 15-month suspension, but fresh concerns are emerging over delayed funding that could threaten the project’s smooth execution.
Contractor BHM International, responsible for the 17-kilometre stretch between the Kpone-Barrier and the Central University campus at Miotso, says the $105 million loan facility earmarked for the project has still not been reinstated.
Client Relations Manager at BHM International, Wisdom Adonoo, speaking to JoyNews after a visit to check progress of work warns that the longer the delay persists, the greater the risk of slowing down or even stalling progress which is scheduled for completion in 18 months.

“We are still waiting for the loan to be reinstated. In the meantime, we are working in good faith based on the minister’s assurance in April, and we are committed to delivering this project on time. But the longer the funds delay, the more difficult it becomes to execute the work as required by contract.”

A visit to the site shows significant improvements compared to five months ago. On the Tema-to-Aflao side, contractors have expanded the road by adding more lanes.

Most sections have already been filled and opened to traffic during peak hours, easing congestion that road users previously complained about.
On the Aflao-to-Accra side, excavation is still ongoing across several stretches, with heavy trucks and machinery actively at work.

BHM says the next phases include stabilisation, stone base pavement, asphalt, and pedestrian walkways, along with the completion of four planned flyovers, three of which already have structures erected.

Beyond funding, compensation for affected residents and traders remains a challenge. According to the Public Relations Officer Pastor Samson Allotey, out of 1,131 people identified for compensation, 842 have so far been paid, representing about 74.5%. Roughly half of those compensated have relocated to allow for construction, but the remaining yet to be compensated threatens work on section of the road.
“We urge government to expedite compensation for the remaining affected persons. Until payments are made and relocations completed, clearance for construction in some areas will remain an issue,” he said.
Latest Stories
-
Ghana, South Korea affirm shared values during bilateral talks
2 minutes -
Dawa Free Zone and GATAC partner to expand diaspora investment opportunities
6 minutes -
Today’s Front pages: Thursday, March 12, 2026
9 minutes -
Ghanaian community in Togo marks 69th independence anniversary
16 minutes -
PETROSOL 2026 Women in Leadership Conference champions female empowerment
35 minutes -
ICU-Ghana honoured at Ghana Development Awards for promoting labour rights
41 minutes -
NYA CEO Osman Ayariga urges youth to build legacies, not just influence
55 minutes -
NYA CEO Osman Ayariga urges youth to think beyond the present at iYES 2026 Summit
1 hour -
Walewale MP calls for probe into alleged irregularities in Auditor-General’s arrears report
1 hour -
Ablakwa’s ISIS strike disclosure puts Ghana at risk – Asafo-Adjei Ayeh
1 hour -
Hudai Foundation, TİKA host Iftar for 1000 orphans at Ghana National Mosque
1 hour -
Ghana hosts IPCC meeting on people-centered climate adaptation
1 hour -
Spiritualist arrested over suspected murder of woman in Awutu Senya
1 hour -
NYA partners iYES 2026 to inspire youth towards transgenerational impact
1 hour -
NYA CEO Osman Ayariga appeals to Wode Maya to champion ‘Red Means Stop’ campaign
1 hour
