SONITRA, a construction firm working on a new interchange close to the entrance of the University of Ghana, has accused the university authorities of derailing work on schedule. Mr Eben Gyampo, Resident Engineer of SONITRA, made the accusation during an inspection tour of the facility on Wednesday by Nii Armah Ashietey, Greater Accra Regional Minister.
The tour, which would in subsequent months also focus on other projects in the region, formed part of the Regional Coordinating Council's mandate to inspect, monitor and evaluate projects within its jurisdiction. Mr Gyampo said Authorities of the University had refused to open to traffic, its (UG's) southern exit road, which joins Tetteh Quarshie to Madina Road at Okponglo Junction, to lessen pressure on the main entrance and thereby allow construction work to progress.
He said the Authorities opined that opening the road to traffic would pose security threats to the institution and that they needed to install security street lights before opening it.
He said two months after SONITRA had finished work on the road the University Authorities had still not opened the southern exit road to traffic because the security street lights have not been fixed.
He said the road was just half a kilometer long, adding for as long as the main entrance remained open to traffic, the company would not be able to undertake construction works on the interchange. Mr Gyampo, therefore, appealed to the government to either fix or impress upon the Authorities of the University to fix the lights to end the unnecessary delay being suffered by the project. SONITRA, in November 2006 won the bid to construct the 4.6 kilometer Tettey Quarshie-Madina three-lane dual carriageway scheduled for completion in May 2009.
Nii Ashietey assured SONITRA of government's support to ensure successful completion of the project adding he would make contacts with sector ministries to liaise with the University Authorities on how best to solve the problem. He said roads were "life-blood" for the country's forward match adding anything that would impede their development would and must be nipped in the bud. "The delays on road projects are costing government huge sums of money because contractors review the contract sums to correspond with current times" he said.
The Regional Minister later toured other project sites including the ongoing rehabilitation of the 5.6 kilometer Madina-Pantang road, rehabilitation of the 3.2 kilometer Kwabenya-ACP-Pokuase road and construction of the Mallam-Tetteh Quarshie road, all of which had reached various stages of completion.
Most of these roads were designed as three-lane and dual carriageways with bridges and overpasses meant to allow for free-flow of traffic in the capital city.
Early on, Nii Ashietey visited the Accra Technical Training Centre (ATTC) to acquaint himself with its operations and challenges to inform how best the RCC could assist it to continue to train young people on skills development.
Mr Ameyaw-Baafi, Principal of ATTC conducted the Regional Minister round some of the departments of the institution.
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
Outstanding challenges in school placement will be addressed before schools reopen – Education Minister
2 hours -
Akufo-Addo to attend NPP National Delegates Conference as party begins rebuilding process
2 hours -
GRA questions GH¢79.65m Servestar Minwax claim, seeks independent audit
2 hours -
PROTOA sets September 21 for indefinite strike over rising transport costs
2 hours -
NPP must unite and rebuild for 2028 – Akufo-Addo
2 hours -
Ex-convict arrested for allegedly posing as soldier and extorting residents in Ashaiman
2 hours -
Diesel could hit GH¢28 without government support – NPA CEO
2 hours -
Four-year water crisis deepens hardship in Agbozume
2 hours -
Denmark, Ghana must deepen green industrial partnership
2 hours -
LEAP new grant rates take effect this month, says Gender Minister
2 hours -
Ghana shifts from advocacy to enforcement on gender equity, disability inclusion
2 hours -
Ho West communities benefit from 2026 big push rural electrification
3 hours -
Dorcas Afo-Toffey pledges to sustain SHS scholarship support in Jomoro
3 hours -
Afo-Toffey Supports 1,000 Jomoro SHS freshers with educational materials
3 hours -
Gender Minister hails Ghana School Feeding Programme
3 hours