AngloGold Ashanti says the Obuasi Redevelopment Project has completed its first week of underground development blasting as the work to pour first gold by the end of the year gathers momentum.
The first blast, at about 7 pm on Friday advanced development by around 4.2 metres on the 2,700 level, which is accessed through the Obuasi Deeps Decline from the surface and is just over 700 metres vertically below the decline portal.
Benching and a number of additional face blasts have taken place since then, with more than 14m of advance recorded.
“The first blast was a significant milestone in transforming this important mine into a modern, productive operation,” said AngloGold Ashanti, Chief Executive Officer, Kelvin Dushnisky.
He added, “Our investment in Obuasi Gold mine’s redevelopment will ultimately make this a key asset for Ghana, and for AngloGold Ashanti’s portfolio, for the long term.”
AngloGold Ashanti announced early last year it would invest $495 million to $545 million to recapitalise the iconic mine in Ghana, to develop its six million ounces of the high-grade reserve.
The project will see Obuasi transformed into a modern, mechanised mine that will produce an average 350,000oz to 400,000oz a year, at all-in sustaining costs of $725/oz to $825/oz, during the mine’s first decade of operation.
Higher grades in the second decade of operation will see production improve further. The project remains on track to produce its first gold by the end of this year, with ramp-up expected during 2020.
AngloGold Ashanti has committed to ensuring significant local content in the mine’s development and operation, through employment at all levels and procurement, notably through the creation of a joint venture between Australia’s AUMS and Ghana’s Rocksure, to undertake Ghana’s underground mining contract.
Development of the project is progressing as planned, and it is expected that capacity will ramp up to around a kilometre of linear advancement per month in the second half of the year.
Stopping operations are expected to start in in the fourth quarter of this year, as new production areas are accessed.
Latest Stories
-
Article 108: Mahama’s legal shield against Anti-LGBTQ Bill?
4 minutes -
2026 FIFA World Cup: Ghana is missing a golden opportunity to sell its tourism, arts, culture to the world
17 minutes -
Peki Girls pedal towards success through Vida Cycling initiative
20 minutes -
Energy Minister backs expansion of Sentuo Refinery
24 minutes -
NDC UK & Ireland marks 47th June 4 anniversary, expands reach with 2 new branches
27 minutes -
South African sprint sensation Mukona “Smiley” Manavhela joins On’s global athlete roster
28 minutes -
World Oceans Day 2026: Why protecting the ocean is critical for climate, jobs and the future of the planet
33 minutes -
What is wrong with us: We mourn the flood but protect the habits that created it
33 minutes -
Ghana Sports Fund pledges support for emerging cycling talent
34 minutes -
The dangerous myth that Panama are Ghana’s easiest opponent at the World Cup
38 minutes -
Coming home: Turning pain into new beginning – Reflections on the return of Ghanaians evacuated from South Africa
39 minutes -
Stakeholders push for sustainable funding for Greater Accra waste
42 minutes -
Ghana reaffirms commitment to sustainable ocean governance on World Oceans Day
47 minutes -
GSA engages high-value shippers on competitive shipping Â
50 minutes -
UN climate talks ‘insensitive’ to continent’s reality, we demand Loss and Damage priority – AGN Chair
53 minutes