Work is steadily progressing on the terminal section of the Boankra Integrated Logistics Terminal (BILT), popularly known as the 'Boankra Inland Port Project'.
This came to light during a recent tour of the project site, following the recommencement of work on the project by Justmoh Construction.
The contract for the recommencement of work on the project was earlier awarded in 2020, after President Akufo-Addo had cut sod for the project which had stalled for many years.
But speaking in an interview with the press, the Project Manager for Justmoh Construction Limited, Saddique Jarrar, said his outfit hit the ground on 10th October this year.
According to him, based on the pace of work, he is optimistic about meeting the deadline in the first quarter of 2024.

“We need to cut and fill the land to have a levelled ground for the terminal area before any construction can start", he added.
The Project covers 413 acres of land. He however revealed that certain portions of the land is waterlogged and has to be worked on.
This he said will require a deep filling with rocks to stabilise the area in order to avert any structural challenges in the future when the terminal starts experiencing heavy traffic.

The Boankra Inland Project, which has been on the drawing board for some eighteen years is expected to be completed by the first quarter of 2024.
When completed, the project will provide service to importers and exporters in the middle and northern parts of the country, and also to act as a major conduit for the efficient transportation of transit traffic to and from neighboring landlocked countries of Burkina Faso, Mali and Niger.

Touching on the prospects of the project, Minister for Transport, Kwaku Ofori Asiamah said the terminal will inure to the benefit of the country, adding that he is also optimistic Justmoh Construction will deliver on its expectations.
Mr. Asiamah said the project forms part of the strategic transport network being developed to bring import and export service to the middle and northern parts of the country.
He noted that government is committed to seeing to the realization of the project.
Residents of Boankra have over the years bemoaned the abandoned project.
However, the renewed works on the project site have calmed their anger and they are hopeful things will turn out as expected.
"I’m glad contractors are on site working their heart out to make the project a reality. After completion, our local economy will flourish”, a farmer envisaged.
Latest Stories
-
Police take over Gomoa Nyanyano after two factions clash in chieftaincy dispute
5 minutes -
Alavanyo Paramount Queen backs Asantehene in opposition to inclusion of Queenmothers in Houses of Chiefs
36 minutes -
OSP’s preventive actions saved Ghana millions – Sammy Darko
1 hour -
Galamsey cuts off cocoa farms in Mfantseman, farmers suffer heavy losses
2 hours -
Ghanaian delegation set for January 20, 2026 trip to Latvia in Nana Agyei case – Ablakwa
3 hours -
Accra turns white as Dîner en Blanc delivers night of elegance and culture
5 hours -
War-torn Myanmar voting in widely criticised ‘sham’ election
7 hours -
Justice by guesswork is dangerous – Constitution Review Chair calls for data-driven court reforms
7 hours -
Justice delayed is justice denied, the system is failing litigants – Constitution Review Chair
8 hours -
Reform without data is a gamble – Constitution Review Chair warns against rushing Supreme Court changes
8 hours -
Rich and voiceless: How Putin has kept Russia’s billionaires on side in the war against Ukraine
8 hours -
Cruise ship hits reef on first trip since leaving passenger on island
9 hours -
UK restricts DR Congo visas over migrant return policy
9 hours -
Attack on Kyiv shows ‘Russia doesn’t want peace’, Zelensky says
9 hours -
Two dead in 50-vehicle pile up on Japan highway
9 hours