The Chief Executive Officer (CEO) of the National Youth Authority (NYA), Mr Pius Enam Hadzide has announced that the Ho Youth Resource Centre will be completed and ready for use in June 2023.
Mr Hadzide made the announcement when he led a team to pay a working visit to the Centre in Adaklu Tsrefe in the Adaklu District.
The visit was to engage the contractor and consultant in charge of the project to inspect the progress of work and identify the fastest way the second phase of the project can be completed on time.

Mr Hadzide disclosed that the entire project is 55 per cent complete and the remaining 45 per cent would be completed by June this year.
He noted that the phase two of the project is about 96% complete, adding that the Centre will soon be fully ready for use.
He said government is constructing 10 youth centres across the country.
"These facilities when completed will host a FIFA standard football pitch, athletic track, a handball pitch among others,” Mr Hadzide said.

The CEO noted that the initial 5000-seating capacity project when completed could accommodate more than that.
Mr Hadzide expressed satisfaction at the progress made so far and urged the contractors to adequately address all challenges associated with the project.
He reiterated government's commitment to making sure that all projects planned for the purpose are completed within the scheduled time.
He commended the Chiefs of Adaklu Tsrefe and Ho for their efforts and support in making sure that the project becomes successful.

Managing Director of Wilkado Construction Limited, Togbe Gbeworza II, in an interview with the media, said “for now, we are able to overcome the initial challenges of clearing the area and the muddy nature of the area.”
He noted that barring any hitches, the second phase of the project will be completed by June ending this year [2023] and handed over to the National Youth Authority.
"For now, they are doing the external works and about to start the fence wall and have come far and with the chiefs solidly behind us over the years, we are grateful and at this point, we crave nothing but your understanding and support," Torgbui Gbeworza II said.
The project which started in 2018 had to be abandoned due to lack of funds.
Latest Stories
-
AAC secures 750 acres of irrigated land to drive commercial vegetable production under MoFA partnership
2 minutes -
Washington wildfire arson suspect twice linked to other blazes, authorities say
5 minutes -
EU hands over two patrol boats to Ghana Navy to boost maritime security
5 minutes -
Fibi Hammond releases new gospel single ‘You Never Fail’
7 minutes -
Muslim and Christian leaders unite against rising student indiscipline in schools
9 minutes -
GSA: New vehicle rules are not a ban on used cars
10 minutes -
Australian teen who killed UK woman has reduced sentence overturned
18 minutes -
Pakistan restricts international media reporting
18 minutes -
Africa spends over US$14bn annually on imported medicines; Ghana must boost local production – Health Minister
27 minutes -
NSMQ 2026: Nifa SHS ends Okuapemman’s four-year run at national championship
28 minutes -
Three confirmed dead in Aboso explosion as police probe suspected illegal storage of explosives
30 minutes -
IMF backs slower fiscal tightening for Ghana from 2027 to allow more development spending
32 minutes -
Michigan Democrats locked in tight battle to earn Senate nomination in crucial seat
32 minutes -
Old Tafo Assembly to intensify sanitation law enforcement as clean-up campaign gathers pace
36 minutes -
New SHS Selection Guidelines: 620,000 students complete School choices as process ends Friday
37 minutes