Audio By Carbonatix
The Electricity Company of Ghana (ECG) says it expects to complete its ongoing major upgrade of key sub-transmission lines in the Greater Kumasi area by June 5, 2026.
According to the company, the project involved upgrading transmission lines from the KNUST Primary Substation to the Kaase Primary Substation, and from Kaase to the Ridge Bulk Supply Point.
In a statement signed by the General Manager for External Communications, Dr Charles Nii Ayiku Ayiku, ECG said the works included replacing existing 265 sqmm conductors with 400 sqmm conductors and changing weak cables to improve power transfer capacity and strengthen electricity supply reliability.

The company noted that the project is expected to improve voltage quality and power supply stability in Kaase, Kuntenase, Sewua, Bekwai and surrounding communities.
ECG further explained that the upgrade will reinforce the sub-transmission connection between the Kumasi 1 (K1) and Kumasi 2 (K2) Bulk Supply Points to improve the resilience of the electricity network within the Ashanti Region.
ECG apologised for the disruptions experienced by customers and residents during the execution of the project, explaining that the temporary inconveniences were necessary to help secure a more reliable power supply for the region.
Latest Stories
-
Don’t just learn AI tools, use them to improve productivity – ALX Enterprise
5 minutes -
Free rabies vaccination campaign targets 25,000 dogs and cats nationwide
11 minutes -
Ghana needs a system to track child protection funding to where risks are highest – ARK Foundation
13 minutes -
AI may not replace humans, but workers who fail to adapt could lose jobs – ALX Enterprise
15 minutes -
Gideon Boako: Bretton Woods is fraying; Ghana has built a bridge
16 minutes -
Ghana’s child protection system failing children despite laws and policies – ARK Foundation
17 minutes -
‘Future of Black Queens is safe for many years’ – Black Princesses boss Charles Sampson
21 minutes -
Titus Glover questions Laboma Beach demolition, proposes widening Kpeshie Lagoon outlet
21 minutes -
NACOC arrests 3 suspects linked to Dutch fugitive drug kingpin
42 minutes -
Workers must complement AI skills with professional expertise to remain relevant – ALX Enterprise
54 minutes -
Companies that delay AI adoption risk losing market opportunities – ALX Enterprise
1 hour -
‘The future is bright’ – Gyan backs Black Princesses squad after U-20 World Cup exit
1 hour -
We should treat AI as an opportunity rather than a threat – ALX Enterprise
1 hour -
Malta and Ghana set sights on practical AI partnership
1 hour -
2026 U-20 WWC: ‘Not all wishes come true’ – Gyan inspires Black Princesses after elimination
1 hour