The Chief Executive Officer of the National Youth Authority (NYA), Osman Abdulai Ayariga, has disclosed that the total cost of refurbishing the Azumah Nelson Sports Complex will only be made public after the project is fully completed.
He explained that ongoing works and adjustments make it premature to put out a final figure at this stage.
Speaking on the project’s status, Mr Ayariga noted that the facility was originally approved in March 2018 as a US$4 million multi-purpose sports complex under the then Minister for Youth and Sports, Isaac Asiamah.
However, the project has experienced prolonged delays over the years, affecting both timelines and projected costs.
According to the NYA CEO, the extended duration of the project is likely to result in an increase in the overall cost compared to the initial estimate.
He added that the focus of the Authority is to ensure that the complex is completed to the required standard and fully equipped to serve its intended purpose.
Mr Ayariga indicated that the refurbishment is now expected to be completed by the end of 2026.
He assured the public that once the project is finished, the full cost details will be disclosed in the interest of transparency and accountability.
Latest Stories
-
ECG to cut power in parts of Accra West on February 11 for planned maintenance
2 minutes -
BoG announces guidelines to govern foreign exchange spot interventions
26 minutes -
Intelligence report uncovers weapons transfers under Sudanese Army oversight to South Kordofan
41 minutes -
119 people died during mediation efforts in Bawku conflict – Mahama
42 minutes -
Trade Ministry to lead raw material expansion for 24-hour production, youth jobs & exports
47 minutes -
Migration induced by coastal erosion: The Shama experience
52 minutes -
Ghana’s economy to expand by 5.67% in 2026
53 minutes -
A/R: ECG surcharges over 2,200 customers for illegal connections, recovers over GH¢4.3bn in 2025
1 hour -
With galamsey still ongoing, who is buying the gold? – Oppong Nkrumah questions gov’t
1 hour -
Avoiding Fiscal Risks in GCR’s deal with GoldBod
1 hour -
Suame Interchange won’t affect NPP votes in Ashanti – Asenso-Boakye
1 hour -
Mahama receives Transition Committee report on UGMC transfer to University of Ghana
1 hour -
Quiz Talk National STEM Programme instituted to boost innovation in basic schools
1 hour -
Unemployed graduates with disabilities engage Gender Minister on jobs and inclusion
2 hours -
Parliament approves GH¢2.9bn for Ghana Medical Trust Fund
2 hours