The Ghana Gas Company is now looking to start commercial production from the gas processing plant in July.
This would be after completing the installation of the plant by the end of June.
The company last year announced that the plant would be ready for production by December 2012. But officials of the company attribute their inability to meet the target to government’s inability to meet some financial obligations on time.
This also affected the supply of equipment being manufactured for the plant.
Dr. George Sipa Yankey, Chief Executive of the Ghana Gas Company, explained to Joy Business: “We were supposed to make down payment 20 days after the date that we signed the agreement, unfortunately for us, the Ministry of Finance delayed in the payment of our contribution of the down payment.
"So early September they warned us that if we didn’t pay within a period of time they are going to suspend work, in September 22 they gave us the final warning and on 24th all works were suspended.”
The 700 million dollar gas infrastructure project will process gas from the Jubilee Field for power generation. The facility is expected to process about 150 million standard cubic of gas a day.
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
UK Fire Aid donates fire tender, equipment to GNFS to boost emergency response
54 minutes -
Man’s hand severed in cutlass clash at Akyem Nkwanum
1 hour -
McIlroy ‘more motivated than ever’ before return
1 hour -
No clear law governs re-arrest of discharged suspects – Justice Abdulai on Hanan, wife re-arrest
1 hour -
GES releases 2026/27 academic calendar; BECE set for May 2027
2 hours -
UCL: PSG beat Bayern on aggregate to set up final against Arsenal
2 hours -
Tariq Lamptey set to have Fiorentina contract terminated – Reports
2 hours -
Four burnt to death in head-on collision at Anyinasin Junction
2 hours -
Ghana, UAE agree to deepen energy and investment cooperation
2 hours -
Old Tafo Assembly cracks down on encroachment at Atimatim Junction
3 hours -
FIFA impose worldwide ban on Benfica’s Prestianni
3 hours -
Kasoa hillside residents fear erosion as climate change intensifies rainfall, experts call for urgent action
3 hours -
Stalled Kumasi, Takoradi market projects to resume as gov’t moves to secure funding
3 hours -
NPP demands release of Hanan Abdul-Wahab, wife, cites abuse of power by EOCO
5 hours -
GES warns schools against unauthorised fee collection from students
5 hours