The Ghana National Gas Company (Ghana Gas) has expressed satisfaction with work on the Atuabo Gas Plant as a test run on the plant proved successful.
A series of tests was carried out over the weekend on the 111-kilometre Onshore pipelines from Atuabo in the Ellembelle district to Aboadze in the Shama district.
The test formed part of the process to check the integrity of the pipeline and to identify and correct potential leakages along the pipeline before the tie-in of the Atuabo Gas Processing Plant (GPP) to the Jubilee field gas reservoirs.
It followed the conclusion of mechanical completion of the Western Corridor Gas Infrastructure Development Project (WCGIDP) and successful hydro-testing of its Offshore Pipeline.

A statement from GGC however, indicated: “During the test, a pin-hole leak was identified at one of the over 10,000 pipe joints laid under the surface of the earth. Appropriate isolation valves have subsequently been engaged and plans for remedial works promptly begun”.
“We are satisfied with the test on the onshore pipeline and we are excited by the fact that just a small portion of the pipeline has thrown up a minor challenge that would be rectified by tomorrow” Director of Operations, Dr Ben Asante, said.
The statement assured the public that “there are no safety concerns whatsoever and we are satisfied with the safety protocol being employed for the testing of the pipeline”.
Latest Stories
-
Man City found guilty of all charges of financial rule breaches, Premier League confirms
16 minutes -
Jeffrey Nortey wins Screen Icon of the Year again at Ghana Entertainment Awards USA
19 minutes -
Man Utd do not deserve Man City titles – Rooney
19 minutes -
Birifoh outdoors new chief: Naa Victor Gandaa V outlines vision for security, education and tourism
20 minutes -
DreamOval Foundation appoints five-member board to drive digital education and youth empowerment
34 minutes -
Accounting for public funds is not enough to prove performance – Ghana Audit Service
35 minutes -
GACC trains journalists on Auditor-General’s NPA Performance Audit Report
35 minutes -
Freedom of expression doesn’t require degradation of public discourse – Bagbin
38 minutes -
NADMO begins relief distribution to over 4,000 households affected by Hohoe floods
53 minutes -
Road Minister tasks Arab Contractors to expedite Kumasi Outer Ring Road
59 minutes -
Media must strengthen fact-checking to fight information disorder – President’s Legal Advisor
1 hour -
DVLA begins pilot of RFID-enabled number plates ahead of 2027 rollout
1 hour -
There is more than one pathway to the future you want
1 hour -
Government appeals to striking teachers to suspend action as FWSC talks resume
1 hour -
Gender Ministry calls for greater industry support for women in TVET
1 hour