Works on the 50-megawatt solar power plant being constructed at Galgu in the Yendi Municipality of the Northern Region, is expected to be completed by November this year.
The construction of the $59 million project, being spearheaded by the Bui Power Authority, began in September 2023, and it would enhance energy security and reliability in the country.
The project that involved the construction of a powerhouse, workers’ accommodation, a five-kilometre access road and other auxiliary works, is currently about 75 per cent complete.
Dr Samuel Kofi Dzamesi, Chief Executive Officer of Bui Power Authority, who led a delegation to inspect the progress of work on the project at Galgu, said it formed part of the government’s commitment to transform the country’s energy sector.
The delegation included Members of Parliament, officials from the Ministry of Energy, Ghana Grid Company Limited and traditional authorities.
Dr Dzamesi said the First Sky Group was the financier and contractor of the project under an engineering, procurement, construction, and financing agreement.
He said: “After completion, we will generate power, sell it, and pay the First Sky Group for eight years.”
“The 140 acres of land provided by the Overlord of Dagbon is sufficient for 100 megawatts. We hope to enter another agreement with the contractor for an additional 50 megawatts after completing this phase,” he added.
Mr Eric Seddy Kutortse, Executive Chairman of First Sky Group, commended the Bui Power Authority for bringing the project to life and the opportunity given to his company to contribute to the nation’s future and lead the charge for sustainable development.
He gave the assurance that the project would be ready for inauguration by November, this year if everything went according to plan.
Mr Emmanuel Adumua-Bossmam, a Deputy Chief of Staff at the Office of the President, said the project was a catalyst for development and would help in creating jobs.
Mr Owuraku Aidoo, Chairman of the Parliamentary Select Committee on Energy, said the project demonstrated Bui Power Authority’s commitment to supporting the country’s renewable energy sector.
Alhaji Salifu Saeed, a Board Member of Bui Power Authority, said the project was evidence of the peace in the Dagbon Traditional Area and called on the people to sustain the peace in the area.
Naa Dr Jacob Mahama, Chief of Zangbalun, who spoke on behalf of Ya-Na Abukari (II), Overlord of Dagbon, lauded the project and said “Solar energy will enable our communities to thrive, foster economic growth and development. So, we are all prepared to give our best in ways that will promote the completion of the project on schedule.”
Latest Stories
-
Education Ministry warns against malpractices as 2026 BECE records early offences
3 minutes -
Ghana eyes Microsoft deal to drive digital jobs and AI growth
13 minutes -
NACOC, Nigeria’s NDLEA sign MoU to strengthen intelligence sharing and joint drug enforcement
39 minutes -
PABF condemns Iranian attacks on UAE, calls for restrain and dialogue
40 minutes -
Photos: Gabon commissions new Congress Centre
41 minutes -
DACF tackles GH¢8bn in unfinished projects nationwide, moves to complete legacy infrastructure
43 minutes -
National Chief Imam urges Ghanaian pilgrims to uphold discipline and unity ahead of 2026 Hajj
50 minutes -
Today’s front pages: Wednesday, May 6, 2026
1 hour -
COP Maame Tiwaa to address Commonwealth Anti-Corruption Conference in Cameroon
2 hours -
Ghana Reference Rate dips to 10.03% in May, signalling possible loan rate cuts
3 hours -
Gov’t evacuates man in viral South Africa xenophobia video attack
3 hours -
From grain pickers to road works: How an Upper West tour shifted Agbodza’s focus
3 hours -
Awoshie-Barnyard crash leaves four seriously injured, triggers heavy traffic
4 hours -
Dog heads don’t prevent heartbreak – ICS debunks growing myth
4 hours -
Flying with two wings: Africa’s opportunity to strengthen economic governance
4 hours