Audio By Carbonatix
The board and management of the Komfo Anokye Teaching Hospital (KATH) in Kumasi have expressed worry over the continued delay in the completion of works on a sickle cell and blood center project for the hospital.
Construction works on the project, which is being sponsored by the Sickle Cell Foundation of Ghana (SCFG) with funding from the Ghana National Petroleum Corporation (GNPC), have come to a halt for more than two years.
The project was to be completed in May 2019 but had to be extended for one year to May 2020.
So far, the first fixing of the plumbing and electrical works have been completed and the building of the basement structure and ground floor has also been finished.
However, further works on the project have been aborted because the contractor had not been paid since August 2020 and at the end of the year 2021, the project was still behind schedule.
This came to light when the Chief Executive Officer of KATH, Dr Oheneba Owusu-Danso, led members of the KATH Board to visit some of the hospital projects under construction.
The visit was to allow the board members to acquaint themselves with the progress of work on the projects and the challenges facing the contractors.
Nana Asibey Opoku, Consultant to the project, told the team that since August 2020, no payment had been made to the contractors, thus accounting for the stalling of the project.
He said the Foundation had lobbied the Asantehene, Otumfuo Osei Tutu II, to press on the GNPC to release funds for the completion of the project.
The GNPC, through the Asantehene in 2016, presented a cheque for $4.5 million to the Sickle Cell Foundation for the construction, tooling, and training of the personnel for the first-ever Sickle Cell and Blood Centre in Ghana at KATH.
Members of the KATH Board who were visibly worried about the situation expressed grave concerns about the delay of the project and said it could affect the cost of the project and further delay its completion.
The board appealed to the GNPC to honour its pledge and pay the contractor to enable them to complete the project.
When completed, the center will serve as a one-stop for the management of all sickle cell cases and blood transfusion-related services for the northern half of the country.
Latest Stories
-
Ghana Water targets the end of January 2026 to resolve Teshie water crises
2 hours -
All UG students who overpaid fees will be refunded – Deputy Education Minister
3 hours -
Majeed Ashimeru set for La Louvière loan switch from Anderlecht
3 hours -
NPP flagbearer race: Any coercion in primaries will be resisted – Bryan Acheampong campaign team
3 hours -
‘Infection spread’ feared: Teshie water crisis triggers healthcare emergency
3 hours -
AratheJay turns ‘Nimo Live’ into defining homecoming moment
4 hours -
NPP race: No official complaint over N/R allegations – Haruna Mohammed
4 hours -
Security analyst warns protocol recruitment eradication will not happen overnight
4 hours -
KGL Foundation commissions ultra-modern Gloria Boatema Dadey-Nifa Basic School at Adukrom
5 hours -
GIMPA reveals GH¢1.7m debt from defaulting sponsored lecturers
5 hours -
PAC cites five GIMPA lecturers for GH¢1.7m bond default
5 hours -
Google confirms that it won’t get Apple user data in new Siri deal
6 hours -
Gomoa Central Special Economic Zone to become first major industrial hub in Central Region – Vice President
6 hours -
Carlos Alberto Pintinho: The ex-Sevilla star who can never play football again
6 hours -
UBA Ghana names Bernard Gyebi Managing Director as bank reorganises top leadership
6 hours
