Chairman of Parliament’s Select Committee on Roads and Transport, Isaac Adjei Mensah, has expressed disappointment in Amandi Construction over delays in completing sections of the Western Railway Line project despite substantial government payments.
The committee raised concerns during a two-day inspection tour of ongoing road and rail infrastructure projects in the Western Region.
The lawmakers inspected the Kojokrom–Manso railway line, a 22-kilometre stretch awarded in 2018 and expected to be completed in 2022.
Although the contractor reportedly claims the project is about 93 per cent complete, members of the committee observed that sections of the project site had been abandoned, with visible deterioration of some structures.

Mr. Adjei Mensah said the committee had directed the consultant supervising the project to provide a detailed report covering the total project cost, government payments made so far, outstanding financial commitments, physical progress of work, and timelines for completion.
“We are disappointed that they have vacated the site and the extent of deterioration in some of the structures,” he stated.
According to him, Amandi Construction is simultaneously handling three rail projects in the area but appears unable to complete the Kojokrom–Manso stretch despite government financial commitments.
“What is happening is that for the three projects, Amandi took all of them and they have just started phases of them, and the excuse is that the government is not paying them,” he said.
The chairman questioned why the contractor had moved on to other projects before completing the existing one.
“I don’t see why they are not able to finish the Kojokrom–Manso line before attending to the others, especially when the government has made substantial payments,” he added.
Mr. Adjei Mensah further noted that if the rail line had been completed, members of the committee could have travelled by train instead of using the road network for their inspection tour.
Vice Chairman of the committee and MP for Sawla-Tuna-Kalba, Andrew Dari Chiwitey, also criticised the pace of work and suggested the contractor may be deliberately delaying projects while pursuing additional contracts.
“We don’t doubt the capacity of Amandi. Amandi is a big company,” he said.
“But what is going on, I am tempted to think that currently they are using delay tactics just to keep the government and the public waiting while they secure more projects.”
He argued that the contractor repeatedly starts projects without completing them before moving on to new ones.
The Vice Chairman also questioned the siting of railway stations in isolated locations away from communities.
“You don’t site stations in the bush. How do you expect community members to access them?” he asked.
He warned that poor accessibility could negatively affect patronage and undermine the purpose of the railway service.
The committee says it expects the consultant’s report to guide further parliamentary action on the delayed projects.
Latest Stories
-
Parliament questions proliferation of unapproved containers in East Legon
6 minutes -
Promotion arrears alone cannot end teachers’ strike — PRETAG
12 minutes -
Ebi Bright alleges assault on driver in dispute with Tema Central MP
18 minutes -
GH¢35m Darkuman 24-hour market to be completed in 16 months — MCE
25 minutes -
NPP risks losing Karaga seat if Amin Adam doesn’t contest – John Boadu
29 minutes -
Ghana Reference Rate falls to 10.04% in October as borrowing costs ease
31 minutes -
53% of NPP delegates backed alternatives to John Boadu in chairmanship race – Mussa Dankwah
34 minutes -
High taxes, water shortages push up hotel operating costs — Hotels Association
35 minutes -
Catholic Bishops demand tougher action on tramadol, marijuana and other drugs
39 minutes -
Government positioning Banda District to become major tourism destination hub – Housing Minister
45 minutes -
Deputy Education Minister appeals to striking teachers to return to classrooms
50 minutes -
Government to involve corporate Ghana in street maintenance – Ayariga
56 minutes -
No contractor is untouchable because of political links — Agbodza
1 hour -
Contractors to resume work on Phase Two of Kejetia Market Project
1 hour -
Government committed to resolving teachers’ concerns - Vice President
1 hour