President Akufo-Addo will on Saturday, November 21 commission the 45KW Tsatsadu Micro Hydro Station at Alavanyo-Abehenease in the Hohoe Municipal Assembly, Volta Region.
In a statement signed by the Corporate Affairs Manager of the Bui Power Authority, Akua Sakyi, the Micro-Hydro Power Generating Station will be the first in the country to be constructed by the Bui Power Authority under the Ministry of Energy’s renewable energy initiative.
The 45kW Tsatsadu Micro Hydro Generating Station, situated on the Tsatsadu Waterfalls, is a run-of-river scheme, which did not require the formation of a reservoir to operate.
It consists of a concrete diversion weir, an intake structure, diversion channel, a forebay, steel penstock, a powerhouse and a transmission line which ties the electricity generated into the local distribution grid.
The weir diverts part of the river flow through an intake channel into the diversion channel.
The diverted water goes through a 300mm diameter penstock to the base of the hill where the powerhouse, which houses the turbines and the generator, is located.
The water drives the turbines and flows out through the tailrace channel and back into the downstream of the waterfall.
The Project, initially designed as a 30kW stand-alone system, was redesigned and upgraded to a 45kW grid connection system based on the outcome of additional studies.
The 45kW Tsatsadu Micro Hydro Generating Station was constructed by local young Engineers of the Bui Power Authority.
The implementation of the 45kW Tsatsadu Generating Station was co-funded by the Danish and Chinese governments through the Renewable Energy Technology Transfer (UNDP-RETT) Project.
The Bui Power Authority collaborated with the United Nations Industrial Development Organization (UNIDO), the International Network on Small Hydro Power of China (IN-SHP) and Ghanaian Energy Sector Agencies to execute the project.
The Bui Power Authority was grateful for the support of the Paramount Chief and people of Alavanyo as well as the Foyer de Charité Catholic Retreat Centre in releasing the portion of their land required for the project.
Latest Stories
-
Fitch affirms ETI at B-; Outlook stable
32 mins -
Bawumia meets Pope Francis
40 mins -
Former Bibiani GoldStars midfielder Frank Adjei Jr continues fine form in Swedish League
44 mins -
J.B. Dankwah Adu’s Murder: Court orders Sexy Dondon to open his defence
47 mins -
Marrakech 2024: Five para-athletes to represent Ghana in WPA Grand Prix in Morocco
59 mins -
U.S Senate approves bill to ban TikTok
1 hour -
T-Pain involved in hit-and-run, warns culprit he’ll find them
1 hour -
Cedi hits GH¢14.00 to a dollar; depreciates 12.08%
1 hour -
Major portions of Kasoa-Winneba road to open to traffic in 8 months
1 hour -
Kwadaso onion traders reject new location, express fear over future eviction
2 hours -
Pensions: 81% of pensioners had benefit shortfalls in 2020 – Abdallah Mashud
2 hours -
All Regional Games: Torch relay ceremony hits Oti Region
2 hours -
CSO calls for immediate removal of COCOBOD CEO from office
2 hours -
How a young female geologist’s thesis is paving the way for Ghana’s Green Mineral Future 5 decades later
2 hours -
Pensions: The last time government paid Tier-2 funds was in June 2023 – Angel Carbonu
2 hours