The Performance Audit Report on Capital Projects funded through District Development Facilities in 30 Districts Assemblies compiled by the Auditor-General has uncovered cases of payment for no work done.
Findings of the Audit Report on payment and work done showed that monies were disbursed for non-executed works resulting in overpayments.
“For example, the pavement for work at the taxi station of Ho barracks was paid in full when only 50 per cent of the work was done.
In some instances, items that were specified for installation were omitted yet payments were made like the U drain around the Bibiani District Police Headquarters, which was not done yet paid in full,” it noted.
The report said in Prestea Huni Valley, the specified depth of the borehole at Gordon Community was 35 to 45 metres for a Mechanised pump however investigations revealed that the depth was not up to that.
“Upon completion of the drilling, an AFRIDEV hand pump recommended for a depth of 16.6 to 30 metres was installed and therefore was not deep enough to pump out water from below 35meter when it was completed and handed over,” it said.
The report said the contractor was paid in full for a mechanised borehole when he provided a manual hand pump borehole and the community had no water.
“We observed that Assemblies make payment for no work done due to insufficient due diligence and familiarisation. In the individual reports, we have recommend for disallowance and Surcharge of the individuals concerned,” it stressed.
The report stated that the occurrences were due to a combination of lack of due diligence on the part of the District Management Team, District Works Engineer (DMEs) and familiarization between DWEs and Contractors.
It said, “Contractors and works engineers get to familiarize with each other to the extent that a suggestion by a contractor for DWE to increase the work done beyond the actual work to cater for delayed payments are accepted and paid for.”
The report said payment for work done except for mobilization was based on measured work at the time of preparing Interim Payment Certificate (IPC).
It noted that the DWEs, upon request by contractors measure the amount of work done, cost it, and prepare certificates to cover the amount.
Per the rule, it said the DMT validates the work against the IPC quantities before approval was given for payment.
Latest Stories
-
GSA defends decision to allow importation of vehicles up to 15 years old
6 seconds -
Sammy Gyamfi distracting Ghanaians from ‘BoG-GoldBod’ losses with extortion allegations – Oppong Nkrumah
22 seconds -
NACOC boss urges prosecutors to uphold integrity and rule of law
1 minute -
Africa must take ownership of its development – Vice President
2 minutes -
African CSOs must diversify funding, reduce donor dependence – WACSI
2 minutes -
Partisan politics, selfish interests stalling Ghana’s housing development – Ahmed Ibrahim
2 minutes -
Government must be limited to powers given by citizens — Kofi Bentil
2 minutes -
GIPA CEO urges businesses to tap capital market
7 minutes -
GIMAT calls for stronger parent-school collaboration to support girls’ health and development
9 minutes -
Xpress Gas, Polygon Energy Technology team up to improve cylinder recirculation model
11 minutes -
Why Ghana has banned unrefined gold exports—GoldBod official provides details
21 minutes -
BoG calls for stronger oversight as Ghana launches Virtual Assets Committee
27 minutes -
mNotify selects 14 SMEs for AI-powered digital transformation programme
30 minutes -
Democracy Cup trophy tour reaches Police Headquarters, NCCE ahead of Kotoko-Hearts clash
34 minutes -
Western Rod and Wire calls for recognition of existing local aluminium rod production
35 minutes