The Performance Audit Report on Capital Projects funded through District Development Facilities in 30 Districts Assemblies compiled by the Auditor-General has uncovered cases of payment for no work done.
Findings of the Audit Report on payment and work done showed that monies were disbursed for non-executed works resulting in overpayments.
“For example, the pavement for work at the taxi station of Ho barracks was paid in full when only 50 per cent of the work was done.
In some instances, items that were specified for installation were omitted yet payments were made like the U drain around the Bibiani District Police Headquarters, which was not done yet paid in full,” it noted.
The report said in Prestea Huni Valley, the specified depth of the borehole at Gordon Community was 35 to 45 metres for a Mechanised pump however investigations revealed that the depth was not up to that.
“Upon completion of the drilling, an AFRIDEV hand pump recommended for a depth of 16.6 to 30 metres was installed and therefore was not deep enough to pump out water from below 35meter when it was completed and handed over,” it said.
The report said the contractor was paid in full for a mechanised borehole when he provided a manual hand pump borehole and the community had no water.
“We observed that Assemblies make payment for no work done due to insufficient due diligence and familiarisation. In the individual reports, we have recommend for disallowance and Surcharge of the individuals concerned,” it stressed.
The report stated that the occurrences were due to a combination of lack of due diligence on the part of the District Management Team, District Works Engineer (DMEs) and familiarization between DWEs and Contractors.
It said, “Contractors and works engineers get to familiarize with each other to the extent that a suggestion by a contractor for DWE to increase the work done beyond the actual work to cater for delayed payments are accepted and paid for.”
The report said payment for work done except for mobilization was based on measured work at the time of preparing Interim Payment Certificate (IPC).
It noted that the DWEs, upon request by contractors measure the amount of work done, cost it, and prepare certificates to cover the amount.
Per the rule, it said the DMT validates the work against the IPC quantities before approval was given for payment.
Latest Stories
-
Emerging agri-journalists gather in Croatia for global event
7 minutes -
PPI Ghana congratulates Dr Abdul-Baasit Aziz-Bamba: Ghana needs a proper reset on value for money
12 minutes -
Kasise Ricky Peprah writes: GBA’s face must be called out – for the record
13 minutes -
Bernice Offei battled dementia for five years before death, former manager reveals
15 minutes -
Jordan Ayew’s return offers Ghana timely boost ahead of AFCON qualifiers
15 minutes -
De Zerbi raises doubts over Kudus’ availability for Ghana’s AFCON qualifiers
25 minutes -
Ghana’s reputation must not be dented by self-centred individuals – Madina MP on cocaine seizure
42 minutes -
MTN Ghana pushes digital growth for SMEs as sixth business clinic ends in Accra.
45 minutes -
Black Maidens confident of WAFU B title defense ahead of Burkina Faso clash
49 minutes -
5 players who deserve a Black Stars call-up for AFCON 2027 qualifiers
1 hour -
Photos: Vice President Jane Naana reviews changing of guard as Ghana Air Force takes over at Presidency
1 hour -
Africa’s richest man launches continent’s biggest share sale
1 hour -
Why Ghana’s MSMEs must rethink human capital investment: Seven strategic benefits
1 hour -
Asutifi South Assembly forms taskforce to stamp out illegal NHIS fees
1 hour -
GBA not politically aligned, we criticise all governments – Deputy Secretary
1 hour