The Performance Audit Report on Capital Projects funded through District Development Facilities in 30 Districts Assemblies compiled by the Auditor-General has uncovered cases of payment for no work done.
Findings of the Audit Report on payment and work done showed that monies were disbursed for non-executed works resulting in overpayments.
“For example, the pavement for work at the taxi station of Ho barracks was paid in full when only 50 per cent of the work was done.
In some instances, items that were specified for installation were omitted yet payments were made like the U drain around the Bibiani District Police Headquarters, which was not done yet paid in full,” it noted.
The report said in Prestea Huni Valley, the specified depth of the borehole at Gordon Community was 35 to 45 metres for a Mechanised pump however investigations revealed that the depth was not up to that.
“Upon completion of the drilling, an AFRIDEV hand pump recommended for a depth of 16.6 to 30 metres was installed and therefore was not deep enough to pump out water from below 35meter when it was completed and handed over,” it said.
The report said the contractor was paid in full for a mechanised borehole when he provided a manual hand pump borehole and the community had no water.
“We observed that Assemblies make payment for no work done due to insufficient due diligence and familiarisation. In the individual reports, we have recommend for disallowance and Surcharge of the individuals concerned,” it stressed.
The report stated that the occurrences were due to a combination of lack of due diligence on the part of the District Management Team, District Works Engineer (DMEs) and familiarization between DWEs and Contractors.
It said, “Contractors and works engineers get to familiarize with each other to the extent that a suggestion by a contractor for DWE to increase the work done beyond the actual work to cater for delayed payments are accepted and paid for.”
The report said payment for work done except for mobilization was based on measured work at the time of preparing Interim Payment Certificate (IPC).
It noted that the DWEs, upon request by contractors measure the amount of work done, cost it, and prepare certificates to cover the amount.
Per the rule, it said the DMT validates the work against the IPC quantities before approval was given for payment.
Latest Stories
-
Mr President, Ghana was mentioned at the UN; why aren’t we talking about it?
45 minutes -
Accra to convene Africa’s regulators and markets on tokenisation at AVAS 2026
47 minutes -
The Paradox of Plenty — When every smartphone becomes a newsroom
1 hour -
GTA sensitises taxi drivers in ‘Know Ghana’ tourism campaign
3 hours -
Archbishop Agyinasare calls for responsible speech amid growing social media abuse
3 hours -
‘It will be inexcusable for gov’t not to honour payment of teachers’ arrears by 30th October’ – Haruna Iddrisu
3 hours -
Forbes’ World’s Best Employers 2026: No Ghanaian firm ranked among 900 companies
3 hours -
Electronic processing of teachers’ data: ‘The decision is the Controller’s’ – GES boss
3 hours -
Teachers’ Strike: Haruna Iddrisu questions paper-based processing of promoted teachers’ data
3 hours -
Savannah Region: Kunfusi bridge collapses again, leaving nearly 4,000 residents cut off
3 hours -
Teachers’ strike: GES targets Monday deadline to submit promotion data to Controller
3 hours -
Inflation to average 11.3% in 2027 – Fitch Solutions
4 hours -
‘I didn’t campaign for NDC to come and do this nonsense’ – Kpebu on EOCO’s conduct
4 hours -
Fitch Solutions maintains policy rate forecast of 14% by December 2026
4 hours -
Diaspora Nasara Caucus congratulates Mohammed Ali Suraj, new NPP executives
5 hours