The over-reliance on the facility for power supply has caused the Bui Hydro-electric plant, which is supposed to be peak-shaving plant, to operate below the recommended minimum operating water elevation of 168 meters above sea level (masl), since mid-March this year, the Institute for Energy Security has said.
“IES study shows that excessive dispatch of the Bui power facility forced the reservoir to drop to its lowest end-December level of 172.22 meters, in three years; despite the reservoir elevation at start 2020 being at 180.33 meters (3.32 meters above 2019 level)”, it said in a statement.
It further said “due to the non-adherence to initial power supply recommendation for 2020, the Bui reservoir elevation dropped to a minimum of 166.82 at the end of May 2021, the lowest recorded since the Bui dam was constructed.”
Data captured from the 2021 Electricity Supply Plan shows that the total hydro electricity generated for 2020 was 7,293.23 gigawatt-hour (GWh) as against the projected of 6,897.2 GWh. This consisted of 5,164.45 GWh, 862.25 GWh and 1,269.52 GWh from Akosombo, Kpong and Bui hydropower facilities respectively.
Further analysis of the data revealed that although the Bui power generation (GS) station was projected to supply 764 GWh to the National Inter-connected Transmission System (NITS) for 2020, the actual supply came up to 1,260 GWh, a deviation of 65 percent from the initial plan.
The Power Planning Technical Committee (PPTC) according to the IES revised the initial planned 764 GWh to 1,218 GWh during the mid-year review of the 2020 Electricity Supply Plan, since the facility had to produce more than anticipated, to fill a supply deficit from other power plants.
First, the IES said “seeing that the drop in elevation below the recommended minimum operating water level was due to over-drafting of the Lake to make up for power supply deficit, the most appropriate measure is to look beyond the Bui facility for peak-shaving this year. Additionally, the Bui facility has to be dispatch in a manner that adequate water could be stored in the reservoir during the 2021 inflow season.”
“Second, noting that the projected total annual hydro generation for 2021 is 7,001 GWh consisting of 5,650 GWh from Akosombo GS, 850 GWh from Kpong GS and 501.2 GWh from Bui GS; fuel supply for thermal plants would be key in determining the reliability of power supply in 202”, it added.
The IES therefore recommended proper coordination to ensure adequate provision of fuels such as Natural gas, Light Crude Oil and Heavy Fuel Oil for the thermal plants, which are expected to generate over 66% of the power required for 2021.
Latest Stories
-
CSIDT proposes 80% of GH¢350m flood budget be invested in prevention
4 hours -
Trump threatens to target Iran’s bridges and power plants if Hormuz attacks persist
4 hours -
Ghana not yet in digital trust crisis, but warning signs are emerging – Kwami Tamakloe
4 hours -
Digital trust crisis looming if fraud concerns are ignored – John Awuah warns
4 hours -
Mamdani backs off pledge to arrest Netanyahu citing lack of authority
4 hours -
Banks’ NPLs drop to 16.1%, but credit risk remains key vulnerability
4 hours -
Business, consumer confidence positive – BoG
5 hours -
We don’t have a trust crisis – BoG urges vigilance against rising digital fraud
5 hours -
GIPC now an authority
5 hours -
Mahama urges African leaders to turn health pledges into concrete investments
5 hours -
NPP Greater Accra Regional Organiser hopeful touts experience, grassroots mobilisation record
5 hours -
WHO warns Africa risks losing decades of health gains as external funding declines
6 hours -
Chief of Staff plants shea tree at Jubilee House to reaffirm government’s commitment to shea industry development
6 hours -
GCB Bank unlocks new pathway to credit with Tier 3 pension-backed loan
6 hours -
Mid-Year Budget: ‘MoU is not a payslip’ – Oppong Nkrumah questions gov’t jobs, economic claims
6 hours