One year from tomorrow, sixteen countries would descend on the Republic of Ghana to participate in the 2008 Africa Cup of Nations.
The event is also expected to bring about two million visitors into the country. As a host nation, Ghana is to provide the infrastructure - stadiums, hotels, communication, transportation and many other services not only for the players and officials but also for the visitors expected and indeed indigenes who would be patronising the matches.
But would the facilities and services be ready by then and would their quality be assured? The contractors are expected to hand over the infrastructure to the Local Organizing Committee (LOC) in October this year but apart from the El-Wark Military Stadium in Accra, which is near completion, the training fields, which the various teams would train on, are yet to see any major construction works.
At Kumasi, the Paa Joe Park, the Opoku Ware Park and the Prempeh College Park are yet to be awarded to contractors. The Gyandu Park and the Railway Park, which would be used by teams that would be based in Sekondi are virtually covered by weeds.
The Baba Yara Sports Stadium in Kumasi and the Sekondi Gyandu Park are yet to be grassed.
As compared to Egypt 2006 and Germany 2006, when the host nations exhibited the fever of the competition a year before the tournament, Ghanaians are yet to show that kind of urgency.
But the Operations Director of the LOC, Mr. Rex Danquah in an unhurried and confident tone told ADM that Ghana would provide the best competition ever witnessed on the continent.
“People are saying we are far behind, but let me tell you, we would complete on time and give the nation the best tournament”, he said.
Mr. Danquah said the training parks would be awarded to contractors next month.
He said the LOC had met with all the Metropolitan, District Assemblies to ensure that they market the event in their various areas of control.
“Even Saturday”, he told ADM “we are launching the countdown to CAN 2008 at all the stadiums”. He debunked the notion that the late re-grassing of the fields would affect quality.
During the 2000 Africa Cup of Nations where Ghana co-hosted with Nigeria, the Baba Yara Sports Stadium had its turf re-grassed, but because it was done in a hurry, the turf did not last long after the competition as it lost its quality.
Mr. Danquah said the LOC is on track and that the contractors would hand all the infrastructure to them by the end of October.
One major and significant development is that the Tamale Sports Stadium is near completion. That is some cause for consolation…but Ghanaians would have to keep all their fingers crossed.
Accra Mail
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
PZ Cussons Ghana promotes hand washing among schoolchildren through Camel campaign
8 minutes -
30 NDC aspirants file nominations in Upper West as regional election approaches
23 minutes -
UPSA launches laptop assembly plant, requiring new students to assemble their own devices
28 minutes -
UCC sociologist calls for action on gender inequality to end child marriage
29 minutes -
LSN questions Ghana’s proposed five-year presidential term and DCE election reforms
30 minutes -
AFCON 2027Q: Bjorkegren to lead Black Stars for Somalia doubleheader with Tanko and Attram as assistants
32 minutes -
AMA completes road repairs on Kwame Nkrumah Avenue
39 minutes -
Law Students’ Network warns executive dominance could undermine constitutional review
41 minutes -
Mahama to meet relevant stakeholders over concerns about the new Customs Act
49 minutes -
CHASS demands a 20% increase in SHS funding and payment of outstanding debts
50 minutes -
Investigation launched after male body found in County Cork
52 minutes -
We have been scammed by NDC, government is only doing PR – Abanga Fuseini
53 minutes -
Tamale Teaching Hospital records 44 new breast cancer cases in six months
55 minutes -
GES declares October 30 CPD day for private school teachers; learners to observe holiday
55 minutes -
South Korea to support Ghana’s forts and castles restoration with $4.5m over five years
56 minutes