The celebrations heralding the arrival of a 225megawatt powership from Turkey, energy expert Amin Adam says, may be short lived because there is no guarantee Karpower will indeed produce power.
The Executive Director of the Africa Centre for Energy Policy, Dr. Mohammed Amin Adam, says government and Ghanaians must tame their excitement because the history of power barge shows it is not a magic wand that will solve Ghana's power crisis.
He was speaking on Joy FM's Super Morning Show day after government held a ceremony to welcome the Karadeniz, which is expected to add 225megawatts to Ghana's energy mix.
There has been a constant media blitz on the Karpower barge with many media houses tracking the ship right from the day it left the shores of Turkey.
Dr. Amin Adam says the enthusiasm must tampered with given that in Lebanon for instance, nine out of the 11 turbines of the powership broke down a few months after the Lebanese government engaged Karadeniz, the barge-constructing company.
The contract was eventually terminated after persistent dissatisfactory performance, he said.

Citizens disgruntled with continues power outages, stage a sit-in blocking the road in Mar Mikhael area in Beirut. (Photo: Marwan Tahtah)
Lebanese History with Karpower
The Karadeniz Powership christened the Fatmagül Sultan, had a 205 MW installed capacity and arrived in Lebanon in February 2013.
It was hailed as “the most practical and rapid solution, both technologically and economically”.
The three-year contract was worth $390 million, whereby the cost of one power-generating ship is $65 million per year.
But the Fatmagul Sultan stationed off the Lebanese coast, stopped producing electricity on April 22, 2013.
Its Turkish owner, the Karadeniz company, maintained that problems were due mainly to low-quality fuel.
Company sources told Al-Akhbar website that the mistake regarding the fuel standards "is not the responsibility of the company, according to the contract agreement."
After more than a month of defaulting in power supply, Karpower demanded $8million in compensation for the downtime.
"The energy ministry is not of this understanding nor is the Turkish company. The ministry will not pay anything for the downtime period," the Lebanese Energy Ministry reportedly replied.

The Lebanese government set up a special tribunal with judges Ramzi Nohra and Lina Hayek investigating the case.
The special tribunal produced minutes of meetings that showed Karadeniz got exactly the fuel quality they wanted and agreed to.
Therefore, the state will have to pay the full contracted amount for the downtime period.
The investigating committee went to the Zouk Energy Plant, where the Fatmagul Sultan is docked, only to be refused access to the ship by the company.
This angered Judge Nohra, who said, "We informed them of our arrival days ahead."
Karadeniz History in Pakistan.
In late 2010, Karkey, the Turkish sister company of Karadeniz Holding won a contract to provide a 232-megawatt capacity as part of a five-year contract worth $565 million.
The power barge arrived at the Karachi Port also carrying aid containers prepared for victims of the Pakistani flood.
It was hailed as the biggest Turkish investment in Pakistan, the ships were said to be capable of supplying 30% of the energy needs of Karachi’s population of 18 million when operated at full capacity.

The Turkish ships that had guaranteed to provide 232 megawatts of power had provided 60 megawatts of power two years into the agreement.
A Karpower company executive explained that although the fuel used for energy generation was to be supplied by the Pakistani government, the supplies were either late or inadequate hence they were incapable of producing the guaranteed amount.
In March 2012, the Supreme Court in Pakistan ruled in favor of terminating the contract signed with Karpower and other power-generating companies.
The court also asked the auditor general to investigate and take the necessary legal measures against those responsible for this issue, after it became clear that the company does not respect the signed agreement.
Karadeniz ventured into the construction of power barges in 2007.
Osman Karadeniz, the company president, has said the idea of floating power stations capable of travelling the world first came to him while in west Africa.
The Africa Center for Energy Policy has asked government to put in its contract with Karpower tougher sanctions if the company fails to perform.
Even though the Power ministry has indicated this barge will not end the power crisis, it is expected to significantly ease the effects of the erratic power supply.
Speaking on the Super Morning Show, Executive Director of the African Center for Energy Policy, Mohammed Amin Adams cautioned the Power ministry to deal with Karpower with the benefit of its history of non-performance.
Latest Stories
-
Let’s give OSP time to mature, not to scrap it – Hassan Tampuli
2 minutes -
Nigeria convicts 386 Islamist militants in mass trials
7 minutes -
Djibouti president wins election with 97.8% of vote, state media saysÂ
12 minutes -
We don’t have mandate to deduct tax from rent allowance of security services personnel – Interior Ministry clarifies
26 minutes -
Ablakwa receives Presidential Special Envoy on Reparations to advance global agenda
44 minutes -
Christina Koch becomes first woman to travel around the moon on Artemis II
54 minutes -
Epstein survivors’ calls to meet King Charles and Queen harder to ignore as US visit approaches
1 hour -
UN Secretary-General names Ghana’s Anita Kiki Gbeho as South Sudan envoy
1 hour -
Mali withdraws recognition of Sahrawi Republic, backs Morocco’s autonomy plan
1 hour -
Gov’t distributes over 8,500 laptops to One Million Coders project
1 hour -
Julius Debrah, ‘man to beat’ as NDC’s James Agbey dismisses Musah Dankwah’s polls
1 hour -
GPRTU in Savannah Region to protest alleged eviction in Damongo
2 hours -
Re: Reinsurance does not replace process — A response to the SIGA–SIC defence
2 hours -
Gender Ministry supports Harriet Amuzu in ongoing abuse case
2 hours -
AG joins plaintiff to scrap OSP ?: We should be mindful of the mischief in this – Bobby Banson
2 hours