The Site Manager for the reconstruction of the 66-kilometre Agona-Nkwanta to Tarkwa road in the Western Region, Peter Quarshie, has said the project is 80 per cent done and expected to be fully completed by the end of August this year.
Mr Quarshie was briefing Mr Francis Asenso-Boakye, the Minster for Roads and Highways, on the state of the road as of April when he toured major ongoing road project sites in the Western Region.
He was accompanied by the Western Regional Minister, Kwabena Okyere Darko-Mensah, officials from the Ghana Highway Authority and Department of Urban Roads, and Metropolitan, Municipal and District Chief Executives, among others.
The project, which started in 2021 at an estimated cost of 95 million Euros, is being undertaken by M/S Gabriel Couto-Rango Consortium, with funding from the Deutche Bank AG, Frankfurt, Germany.
Mr Quarshie explained that the scope of the reconstruction of the stretch included concrete works which entailed building drains, and pipe and box culverts.
Others were the application of bituminous prime coat, bituminous tack coat, asphaltic concrete binder course and asphaltic concrete wearing course.
The rest were the provision of walkways, medians, streetlights, traffic signs and markings including road line markings, information, warning and mandatory signs, and kilometre posts.
He assured the Roads and Highways Minister that the contractor would work assiduously to meet the project deadline of August 30.
Mr Asenso-Boakye expressed satisfaction at the progress on site and commended the contractor for the quality of work done so far.
He said the project, upon its completion, would facilitate socio-economic activities to enhance the living standards of the people along that corridor.
Mr Asenso-Boakye said the government would do everything in its capacity to provide good road infrastructure in other areas of the country for sustainable growth.
He went round other areas to assess progress of ongoing projects like the Sekondi to Takoradi road dualisation, and sectional repair works on Nkroful Junction–Ketan to Kojokrom Junction- Kojokrom Market Road on the main Takoradi to Cape Coast highway, which were at various stages of completion.
The rest were the proposed road construction at Mpohor, dualisation of Takoradi to Agona-Nkwanta, and Shama Junction-Shama roads.
Latest Stories
-
Ablekuma North MP donates relief items to flood victims
28 minutes -
AMA presents 997 school desks to improve teaching and learning in public schools
1 hour -
Beyond drains: Susan Adu-Amankwah prescribes lasting solution to Accra floods
2 hours -
GES, UMA-Subika hold reading competitions to boost literacy in Asutifi North
2 hours -
Ashanti Regional Minister, Zoomlion launch sustained sanitation campaign in Ashanti
4 hours -
Muzic Mensah earns four nominations at 2026 Ghana Music Awards USA
5 hours -
2026 U17 WWCQ: Black Maidens snatch late draw in first leg against Senegal
6 hours -
Flood mitigation should be continuous, not a one-off effort – Expert warns
6 hours -
From Tragedy to Triumph: Ghana’s path to flood resilience (A Story of Lessons Learned, Global Inspiration, and a Collective Commitment to a Better Future)
6 hours -
Kristo Asafo dispute centres on my father’s final directives, not inheritance — Adwoa Safo
6 hours -
Kristo Asafo saga: ‘My dad didn’t die intestate; he left a valid will’ – Adwoa Safo
6 hours -
New Eastern Regional Fire Commander tours stations, identifies key operational challenges
7 hours -
Government fully responsible for Accra flooding crisis – Miracles Aboagye
7 hours -
Successive governments have failed to address flooding crisis – Susan Adu-Amankwah
7 hours -
No one can hold title on Ramsar sites – Inusah Fuseini warns against encroachment
7 hours