The Site Manager for the reconstruction of the 66-kilometre Agona-Nkwanta to Tarkwa road in the Western Region, Peter Quarshie, has said the project is 80 per cent done and expected to be fully completed by the end of August this year.
Mr Quarshie was briefing Mr Francis Asenso-Boakye, the Minster for Roads and Highways, on the state of the road as of April when he toured major ongoing road project sites in the Western Region.
He was accompanied by the Western Regional Minister, Kwabena Okyere Darko-Mensah, officials from the Ghana Highway Authority and Department of Urban Roads, and Metropolitan, Municipal and District Chief Executives, among others.
The project, which started in 2021 at an estimated cost of 95 million Euros, is being undertaken by M/S Gabriel Couto-Rango Consortium, with funding from the Deutche Bank AG, Frankfurt, Germany.
Mr Quarshie explained that the scope of the reconstruction of the stretch included concrete works which entailed building drains, and pipe and box culverts.
Others were the application of bituminous prime coat, bituminous tack coat, asphaltic concrete binder course and asphaltic concrete wearing course.
The rest were the provision of walkways, medians, streetlights, traffic signs and markings including road line markings, information, warning and mandatory signs, and kilometre posts.
He assured the Roads and Highways Minister that the contractor would work assiduously to meet the project deadline of August 30.
Mr Asenso-Boakye expressed satisfaction at the progress on site and commended the contractor for the quality of work done so far.
He said the project, upon its completion, would facilitate socio-economic activities to enhance the living standards of the people along that corridor.
Mr Asenso-Boakye said the government would do everything in its capacity to provide good road infrastructure in other areas of the country for sustainable growth.
He went round other areas to assess progress of ongoing projects like the Sekondi to Takoradi road dualisation, and sectional repair works on Nkroful Junction–Ketan to Kojokrom Junction- Kojokrom Market Road on the main Takoradi to Cape Coast highway, which were at various stages of completion.
The rest were the proposed road construction at Mpohor, dualisation of Takoradi to Agona-Nkwanta, and Shama Junction-Shama roads.
Latest Stories
-
Teshie launches Homowo 2026 with renewed commitment to peace, security and cultural heritage
1 hour -
Maritimo target Ghanaian winger Nana Kofi Donkor after impressive season in Georgia
4 hours -
Ghanaian youngster Isaac Assibu signs new Malmo deal, earns first-team promotion
5 hours -
Prince Owusu completes four-year move to DAC 1904
5 hours -
When Politics Meets Perception: Will Ken Ofori-Atta return to Ghana?
8 hours -
Peace must be the hallmark of Homowo 2026 – DCOP Asiedu
9 hours -
‘Ghana lost a president, but I lost a mentor and a friend’ – Mahama pays tribute to Atta Mills
9 hours -
Ghana’s High Commissioner to UK commits to support Team Ghana at Commonwealth Games
10 hours -
Photos: Flood Mitigation Task Force begins phased dredging, demolition exercise in Accra
10 hours -
ICC top prosecutor removed over sexual misconduct allegations
10 hours -
Glasgow 2026: Ghanaian boxer Abdul Wahid Omar eliminated after unanimous points defeat to Patris Mughalzai
10 hours -
Ghana Gas CEO Judith Adjobah Blay earns Master of Laws degree from University of Nottingham
10 hours -
Gender Minister leads monitoring exercise to strengthen School Feeding Programme
10 hours -
Gov’t advocates capacity building for Ghana’s creative industry at interior design masterclass
10 hours -
Flood Mitigation Task Force begins phased dredging, desilting and demolition exercise across various locations in Accra
10 hours