The Site Manager for the reconstruction of the 66-kilometre Agona-Nkwanta to Tarkwa road in the Western Region, Peter Quarshie, has said the project is 80 per cent done and expected to be fully completed by the end of August this year.
Mr Quarshie was briefing Mr Francis Asenso-Boakye, the Minster for Roads and Highways, on the state of the road as of April when he toured major ongoing road project sites in the Western Region.
He was accompanied by the Western Regional Minister, Kwabena Okyere Darko-Mensah, officials from the Ghana Highway Authority and Department of Urban Roads, and Metropolitan, Municipal and District Chief Executives, among others.
The project, which started in 2021 at an estimated cost of 95 million Euros, is being undertaken by M/S Gabriel Couto-Rango Consortium, with funding from the Deutche Bank AG, Frankfurt, Germany.
Mr Quarshie explained that the scope of the reconstruction of the stretch included concrete works which entailed building drains, and pipe and box culverts.
Others were the application of bituminous prime coat, bituminous tack coat, asphaltic concrete binder course and asphaltic concrete wearing course.
The rest were the provision of walkways, medians, streetlights, traffic signs and markings including road line markings, information, warning and mandatory signs, and kilometre posts.
He assured the Roads and Highways Minister that the contractor would work assiduously to meet the project deadline of August 30.
Mr Asenso-Boakye expressed satisfaction at the progress on site and commended the contractor for the quality of work done so far.
He said the project, upon its completion, would facilitate socio-economic activities to enhance the living standards of the people along that corridor.
Mr Asenso-Boakye said the government would do everything in its capacity to provide good road infrastructure in other areas of the country for sustainable growth.
He went round other areas to assess progress of ongoing projects like the Sekondi to Takoradi road dualisation, and sectional repair works on Nkroful Junction–Ketan to Kojokrom Junction- Kojokrom Market Road on the main Takoradi to Cape Coast highway, which were at various stages of completion.
The rest were the proposed road construction at Mpohor, dualisation of Takoradi to Agona-Nkwanta, and Shama Junction-Shama roads.
Latest Stories
-
GES release national harmonised prospectus for 2026/2027 SHS admissions
29 seconds -
Presidency orders TMA, TDC to end dispute over Tema development authority
6 minutes -
Ayew brothers among Ghanaians without clubs after transfer window closes
25 minutes -
GPHA records GH¢2.82bn net profit as revenue rises to GH¢7.62bn
32 minutes -
Today’s front pages: Thursday, September 3, 2026
37 minutes -
Police arrest over 10 students over Okuapeman-Mount Sinai clashes
53 minutes -
WAFU B WCLQ: Ampem Darkoa Ladies thrash Dynamique FC to reach final
2 hours -
Chief Justice should avoid partisan political arena – Prof Kwaku Asare
2 hours -
GMTF Administrator hails Mintah Akandoh’s support as Fund marks first year
2 hours -
GPHA honours 410 staff for outstanding service
3 hours -
BoG slashes September FX support to $500m as GoldBod boosts dollar supply
3 hours -
GNFS rolls out automated fire compliance system
3 hours -
SOE profit at GH¢19.8bn: I call it a miracle, but it’s not operational efficiency – Dr Atuahene
3 hours -
SHS violence: Government must review discipline policy – IFEST
3 hours -
Nana Akomea leads NPP First Vice Chairman race in new poll
3 hours