Audio By Carbonatix
The Director-General of the Department of Urban Roads, James Oduro Amoo-Gottfried, says the local roads component of the Suame Interchange Phase Two project will be fully completed and opened to traffic by October 2026.
He says the completion of the project will provide alternative routes for motorists and help reduce traffic congestion in the Suame area.
Speaking at a stakeholders’ engagement in Kumasi, Ing. Amoo-Gottfried said work on both phases of the Suame Interchange project was progressing steadily.
He explained that Phase One involves the construction of the main multi-tier interchange, including an overpass from the Suame Roundabout to Abrepo Junction, as well as the widening of the road along the Western Bypass.

Phase Two, he said, covers approximately 15 kilometres of local roads within the project’s area of influence.
According to him, the second phase is almost complete and includes the construction of three overpasses at Anomangye, New Road and Ebusuakruwa.
Ing. Amoo-Gottfried explained that Phase Two was being completed ahead of Phase One to provide alternative routes for motorists when construction works on the main interchange begin.
“Phase Two is almost complete, and hopefully by the end of October, we would have opened the road to traffic and allowed people to use it,” he said.
He added that the overpasses would improve northbound traffic movement within the area and provide additional routes for motorists.

On the main corridor between the Suame Roundabout and Abrepo Junction, the Director-General said the road would be widened to increase vehicular capacity and ease congestion.
He noted that a grade-separated underpass would also be constructed at Abrepo Junction, one of the busiest points along the corridor.
He explained that traffic from Bantama and the hospital area would pass underneath the junction directly towards Abrepo, while vehicles using the bypass would continue at ground level.
“Between Suame Roundabout and Abrepo Junction, we’ll widen the road to allow for more vehicles. But most importantly, at Abrepo Junction, which is a heavily congested area, we are going to grade-separate it and create an underpass.
So when you are coming from Bantama, the hospital area, you go under straight to the Abrepo area. But when you are on the bypass, you’ll be on a level ground.”
The Director-General also addressed concerns over traders and other structures located within the project’s right of way.
He said persons operating within the affected areas were there on a temporary basis and that the Suame Municipal Assembly would engage them to facilitate their relocation and allow construction works to proceed.
“We have engaged the Assembly, and the Assembly will deal with them. For some of them, the Assembly is the one that had the arrangement for them to be there temporarily.
So the Assembly will deal with them to move out, so that we can do the work. The time is now for us to do it, so that we can all be comfortable. It’s almost immediate,” he stated.
Latest Stories
-
NPA uses Fetu Afahye to educate consumers on petroleum safety
3 minutes -
Roads Minister orders contractors to keep working during official visits
13 minutes -
New 4-year bond attracts GH¢4.46bn in bids
13 minutes -
AIA VIP Lounge to be completed without taxpayer funds – Ablakwa
17 minutes -
KEEA Assembly disburses GH¢267,518 to 94 PPCs in third quarter
20 minutes -
Dr Abu Sakara urges African youth to lead economic freedom
25 minutes -
24-Hour Economy mobilises GH¢1bn for poultry value-chain transformation
31 minutes -
From working in his room to building a business group – Michael Bartlett-Vanderpuye’s journey
32 minutes -
SOEs dividend contributions fall 45.5% in 2025- Report
39 minutes -
DBG steps up textile industry financing with new investor-ready projects
43 minutes -
GPL: Hearts make emphatic winning start, Debibi United hold Kotoko
45 minutes -
Middle East conflict disrupts Ghana’s gold exports as first-half volumes dip
1 hour -
BoG to roll out crypto guidelines soon, clear path for licensing – Asiama
1 hour -
DBG lines up textile deals for credit approval, disbursement before year-end
2 hours -
DBG channels billions into businesses private banks struggle to finance
2 hours