Audio By Carbonatix
The Volta Aluminum Company Limited will effect from Friday, March 16 suspend its operations due to inadequate power supply from the Akosombo Dam.
The shut down, the 11th in the history of VALCO since its establishment in 1967 will result in declaring majority of the 700 labour force redundant.
Dr Charles Mensa, Chief Executive officer of the smelting plant which the state has 90 percent shares with 10 percent for ALCOA, described the latest action as regrettable and a disappointment to those who looked up to VALCO to realize the late President Nkrumah’s dream of industrialization.
He explained that the decision to shut down was voluntary when the company realised the declining level of water in the Akosombo Dam.
He said about 200 staff members would be retained too secure and maintain the plant.
Dr Mensa said the skeleton staff would build an extrusion and rod-mill plants in readiness for power to provide the environment for the country’s industrialization and the creation of jobs.
He said the shut down would offer the management of VALCO the challenge to develop alternative sources of power.
According to Dr Mensa, in the interim the extrusion and rod-mill would help to produce aluminum doors and windows and transmission lines for electricity.
He said the long term objective of VALCO was to develop a coal fired power plant to take the smelter plant off the national grid.
Dr Mensa explained that it was expected that it would take VALCO a minimum of 24 months to develop the plant, adding that VALCO was working with an independent power provider to start the construction as early as possible.
He said the plant, which will cost about $400 million to construct, would generate about 500 megawatts of power.
Dr Mensa said to enable VALCO to produce full capacity, the company required about 350 megawatts of power.
He said when VALCO achieved that objective; it would be in a position to give the surplus power to the state to improve the capacity of the national grid by about 150 megawatts.
Asked whether the use of coal to power a big smelter like VALCO was outdated, Dr Mensa discounted that claim and explained that coal was readily available in Enugu, Nigeria and Southern African countries.
He said VALCO could no longer rely on electricity to run the plant, adding that an investment whose raw material was electricity could no longer be predicted.
Dr Mensa said VALCO was better off generating its own power and taking control of its operations.
Source: Daily Graphic
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
‘Development must not always begin from Accra’ — Anwelle Foundation launched in Jirapa
1 minute -
PKO trio eye victories at Odwira Festival
3 hours -
346 Ghana Navy recruits pass out after 26 weeks of intensive training
3 hours -
Newsfile to discuss EOCO-MP arrest, drug trafficking, speech arrests and $235m water debt
3 hours -
JoyNews gets results as listeners raise GH¢40,000 to help 17-year-old student with cerebral palsy attend SHS
4 hours -
Vice President calls for stronger local pharmaceutical production to reduce medicine imports
4 hours -
The brewing tension at KNUST; Beware the Ides of October….
4 hours -
Health Ministry moves to integrate traditional medicine into mainstream healthcare
5 hours -
550 pupils in Kintampo South get educational lifeline as ‘Seeds of Hope’ reaches farming communities
5 hours -
Opoku Mensah urges Christian Council, House of Chiefs to speak up on democratic freedoms
5 hours -
Teacher unions’ strike: Minority demands immediate payment of teacher arrears, 20% deprived area allowance
5 hours -
The Accra-Kumasi Expressway: Building it right
6 hours -
Beyond gold exports: Building value and economic resilience from Ghana’s gold
6 hours -
2027 AFCONQ: Ghana under pressure as Gambia beat Somalia 2-1
6 hours -
Eastern NPP Women’s Organiser calls on AG, Police to secure bail for Salomey Baffoe
6 hours