Public Relations Officer for the Pwalugu Dam Project, David Prah, says work on the $1 billion facility has only stalled because of the Bagre Dam spillage and resultant flooding.
Speaking to JoyNews’ Kojo Yankson, he explained that the main area at which the construction is supposed to take place has been submerged in water.
Continuing work on the project will only lead to inaccurate readings which will affect their output, Mr Prah stated.
“It is very prudent and wise that you stay off and let the danger recede so that you can proceed. We need to demarcate properly and lift what we have on the drawings to the site,” he added.
The Pwalugu Dam has been touted as the solution to the perennial flooding which ravages three regions in Northern Ghana.
The proposed multi-purpose dam will also benefit the region’s population in terms of irrigation development, flood management as well as power generation.
Meanwhile, Mr Prah says that they are ready to hire about 1200 people for the construction of the dam when the work resumes.
He revealed that there had been demarcations for a campsite to house the workers.
“The construction of dams is not one or two days affair,” The PRO added.
However, Kobina Yakubu, the carpenter who now serves as a caretaker at the stalled construction site, said that the Chinese constructors have moved to work on the Tamale Interchange.
He told Kojo Yankson that the foreign constructors had said they are waiting for some money owed them before they return to the dam's site.
Latest Stories
-
FDA warns of fake HIV test kits on Ghanaian market
10 minutes -
Africa urged to build resilient health systems as donor support tightens
16 minutes -
Easter gesture: Ablakwa settles medical bills for 85 North Tongu constituents
2 hours -
Africa must harness its population strength—Titus-Glover
2 hours -
Visa-free access doesn’t mean unlimited stay – Lom Ahlijah
2 hours -
From Golgotha to Kwahu: The Easter Migration of the Faithful and the Faithless
3 hours -
How the Ghanaian onion traders’ standoff with Nigeria unfolded and threatened local supply
4 hours -
No compensation for demolished structures on 24-Hour Economy market lands — Gov’t to structure owners
4 hours -
Financial Institutions must back local enterprises to spur growth – Deputy Minority Whip
4 hours -
Photos: Gomoa Easter Carnival 2026 ends in a burst of colour and celebration
4 hours -
Gomoa Easter carnival ends in colour as fashion, music and celebrity appearances light up final night
4 hours -
Families pick Luv Fm Family Party to celebrate Easter Monday with music and more
5 hours -
IMANI flags procurement issues in Ghana Gas insurance switch
5 hours -
Kaneshie footbridge rehabilitation to take up to 9 months — AMA
5 hours -
AMA confirms trading will be banned on Kaneshie footbridge after rehabilitation
5 hours